7 line items · $6M · starting 2026 · 1 plan
Sandpoint's published capital plans list 7 water, sewer and wastewater line items with a combined planning budget of $6M, of which 4 items worth $2M sit in the wastewater and sewer departments. The largest single item is Watermain Projects at $3M (2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Watermain Projects | Water Distribution | Water mains and distribution | $3M | 2026 |
| 2 | Lower Diversion Upgrades | Water Supply | Headworks, screening and grit | $1M | 2026 |
| 3 | Wastewater Main Line Replacement | Sewer | Water mains and distribution | $620K | 2026 |
| 4 | Sewer Lift Station Replacements | Sewer | Lift stations | $400K | 2026 |
| 5 | Wastewater Treatment Facility Phased Reconstruction | Wastewater | Wastewater treatment plant upgrades | $300K | 2026 |
| 6 | Inflow and Infiltration (I/I) Reduction | Sewer | Membranes and filtration | $280K | 2026 |
| 7 | Little Sand Creek Watershed Management Plan, Timber Management Plan & Urban Forestry Master Plan Projects | Water Supply | Planning, studies and asset management | $250K | 2026 |
Descriptions, page references and contacts for Sandpoint
Klarifi holds every Sandpoint line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.
2026
$6M
7 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 1 | $300K | 5% |
| Sewer | 3 | $1M | 23% |
| Water Supply | 2 | $2M | 27% |
| Water Distribution | 1 | $3M | 45% |
1 publicly owned treatment plant in Sandpoint with 2 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Kootenai-Ponderay WWTP | — | ID0021229 | 2 |
Sources and methodology
Budgets and years are as published in Sandpoint’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2026–2030 (7 line items).
Data refreshed September 11, 2026.