Sandpoint, Idaho: water and wastewater capital improvement projects

7 line items · $6M · starting 2026 · 1 plan

Sandpoint's published capital plans list 7 water, sewer and wastewater line items with a combined planning budget of $6M, of which 4 items worth $2M sit in the wastewater and sewer departments. The largest single item is Watermain Projects at $3M (2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Sandpoint

The 7 largest water, sewer and wastewater line items in Sandpoint’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Watermain ProjectsWater DistributionWater mains and distribution$3M2026
2Lower Diversion UpgradesWater SupplyHeadworks, screening and grit$1M2026
3Wastewater Main Line ReplacementSewerWater mains and distribution$620K2026
4Sewer Lift Station ReplacementsSewerLift stations$400K2026
5Wastewater Treatment Facility Phased ReconstructionWastewaterWastewater treatment plant upgrades$300K2026
6Inflow and Infiltration (I/I) ReductionSewerMembranes and filtration$280K2026
7Little Sand Creek Watershed Management Plan, Timber Management Plan & Urban Forestry Master Plan ProjectsWater SupplyPlanning, studies and asset management$250K2026

Descriptions, page references and contacts for Sandpoint

Klarifi holds every Sandpoint line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

2026

$6M

7 items

By department

Line items and planning budgets by department, Sandpoint.
DepartmentLine itemsBudgetShare
Wastewater1$300K5%
Sewer3$1M23%
Water Supply2$2M27%
Water Distribution1$3M45%

Wastewater treatment plants in Sandpoint

1 publicly owned treatment plant in Sandpoint with 2 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
Kootenai-Ponderay WWTPID00212292

Other Idaho cities with capital plans

Sandpoint capital plan questions

Sources and methodology

Budgets and years are as published in Sandpoint’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2026–2030 (7 line items).

Data refreshed September 11, 2026.