Boulder City, Nevada: water and wastewater capital improvement projects

6 line items · $5M · starting 2026–2027 · 1 plan

Boulder City's published capital plans list 6 water, sewer and wastewater line items with a combined planning budget of $5M, of which 4 items worth $2M sit in the wastewater and sewer departments. The largest single item is Copper Service Replacement at $2M (2026–2030). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Boulder City

The 6 largest water, sewer and wastewater line items in Boulder City’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Copper Service ReplacementWater DistributionSewer rehabilitation and I&I$2M2026–2030
2Sanitary Sewer UpgradeSewerSewer rehabilitation and I&I$1M2027–2030
3Sewer Line Relocation (Georgia at Buchanan)SewerSewer rehabilitation and I&I$750K2026
4Effluent Splitter Box ImprovementsSewer$340K2026
5Concrete Lined Aeration Basin ImprovementsSewerAeration and blowers$200K2026
6Replace Unit 313 - Dump TruckWater DistributionVehicles and equipment$150K2026

Descriptions, page references and contacts for Boulder City

Klarifi holds every Boulder City line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

2026

$4M

5 items

2027

$1M

1 items

By department

Line items and planning budgets by department, Boulder City.
DepartmentLine itemsBudgetShare
Sewer4$2M49%
Water Distribution2$3M51%

Wastewater treatment plants in Boulder City

No publicly owned treatment plant is recorded under Boulder City in the facility directory; the city may be served by a regional plant listed under another municipality. Browse all plants in Nevada.

Other Nevada cities with capital plans

Boulder City capital plan questions

Sources and methodology

Budgets and years are as published in Boulder City’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2026–2030 (6 line items).

Data refreshed September 11, 2026.