28 line items · $48M · starting 2026–2028 · 1 plan
Carson City's published capital plans list 28 water, sewer and wastewater line items with a combined planning budget of $48M, of which 14 items worth $28M sit in the wastewater and sewer departments. The largest single item is Wastewater Line Replacement/Rehabilitation Program at $10M (2025–2029). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Wastewater Line Replacement/Rehabilitation Program | Wastewater | Water mains and distribution | $10M | 2025–2029 |
| 2 | Water Line Replacement/Rehabilitation Program | Water Distribution | Water mains and distribution | $7M | 2025–2029 |
| 3 | Future Plant Upgrades | Wastewater | — | $5M | 2027–2029 |
| 4 | Septic Receiving | Wastewater | — | $3M | 2025–2026 |
| 5 | Quill Treatment Plant Rehabilitation/Refinements | Water Supply | Wastewater treatment plant upgrades | $3M | 2025–2026 |
| 6 | Undesignated - Infrastructure Capital | Wastewater | — | $2M | 2025 |
| 7 | Undesignated - Infrastructure Capital | Water Supply | — | $2M | 2025 |
| 8 | Vehicle Replacement Program | Water Supply | Vehicles and equipment | $2M | 2025–2029 |
| 9 | Septic Conversion Program | Wastewater | — | $2M | 2027 |
| 10 | Equipment Repair and Maintenance WRRF/Lines | Wastewater | Wastewater treatment plant upgrades | $1M | 2025–2029 |
18 more line items in Carson City, with descriptions and contacts
Klarifi holds every Carson City line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$40M
22 items
2026
$792K
1 items
2027
$6M
3 items
2028
$1M
2 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 14 | $28M | 59% |
| Water Supply | 10 | $10M | 21% |
| Water Distribution | 4 | $9M | 19% |
No publicly owned treatment plant is recorded under Carson City in the facility directory; the city may be served by a regional plant listed under another municipality. Browse all plants in Nevada.
Sources and methodology
Budgets and years are as published in Carson City’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.