Exeter, New Hampshire: water and wastewater capital improvement projects

9 line items · $14M · starting 2026–2028 · 1 plan

Exeter's published capital plans list 9 water, sewer and wastewater line items with a combined planning budget of $14M, of which 8 items worth $8M sit in the wastewater and sewer departments. The largest single item is Groundwater Source Development at $7M (2025). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Exeter

The 9 largest water, sewer and wastewater line items in Exeter’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Groundwater Source DevelopmentWater SupplyWells and groundwater$7M2025
2High Street/Cross Country Sewer RehabSewerSewer rehabilitation and I&I$3M2026
3WWTF Upgrades Phase IWastewaterWastewater treatment plant upgrades$3M2027–2028
4Clemson LagoonWastewaterLagoons and ponds$500K2025
5Court Street Pump StationSewerPump stations$500K2027
6WWTF Effluent FlumeSewerWastewater treatment plant upgrades$245K2025
7Intersection Improvements - Front StreetSewerSewer rehabilitation and I&I$150K2025
8Portsmouth Ave DesignSewerSewer rehabilitation and I&I$94K2028–2029
9#51 Jeep - ReplacementWastewaterWastewater treatment plant upgrades$32K2026

Descriptions, page references and contacts for Exeter

Klarifi holds every Exeter line item with its description, the page it appears on and the source document, plus 18 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

Before 2026

$8M

4 items

2026

$3M

2 items

2027

$3M

2 items

2028

$94K

1 items

By department

Line items and planning budgets by department, Exeter.
DepartmentLine itemsBudgetShare
Wastewater3$3M23%
Sewer5$4M30%
Water Supply1$7M47%

Wastewater treatment plants in Exeter

1 publicly owned treatment plant in Exeter with 18 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
Exeter Wastewater Treatment Facility1.1NHG58A00418

Other New Hampshire cities with capital plans

Exeter capital plan questions

Sources and methodology

Budgets and years are as published in Exeter’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2025–2030 (9 line items).

Data refreshed September 11, 2026.