North Slope Treatment Plant

007 1st Avenue, Moline, IL 61265 · Rock Island County · Publicly Owned Treatment Works

Average flow
4.25 MGD
Design flow
—
NPDES permit
ILL029947
Effective
Permit expires
December 2030
Population served
15,605
CWNS 2022

North Slope Treatment Plant is a publicly owned wastewater treatment works in Moline, Rock Island County, Illinois treating an average of 4.25 million gallons per day, serving about 15,605 residents. It discharges under NPDES permit ILL029947 (effective), which expires in December 2030, with 1 recorded violation in the last three years. EPA has recorded 1 formal enforcement action naming the plant, the latest in September 2026.

Treatment technology

One treatment structure or unit process identified at North Slope Treatment Plant.

Available with a free Klarifi account

See the full treatment train at North Slope Treatment Plant: structures, unit processes and planned upgrades, with exact unit counts.

Create a free account

Compliance snapshot (last 3 years)

Total violations
1
Effluent violations
1

Based on NPDES Discharge Monitoring Reports. Full violation history, parameters and discharge data available in the Klarifi platform.

EPA enforcement history

Federal civil enforcement cases, compliance inspections and informal actions recorded for North Slope Treatment Plant in EPA's ICIS system.

Formal actions
1
1 since FY2020
Compliance actions
$15,000
required by EPA orders
EPA inspections
1
none on record

Latest case · Sep 2026

Moline_AOC

Administrative order · CWA, NPDES Permit Violations · Final Order No Penalty · Compliance actions $15,000 · The case also names 1 other plant, and its amounts cover all of them

Source: EPA ECHO, civil enforcement case 05-2024-0318.

Full case history with a free Klarifi account

Every action against North Slope Treatment Plant with dates, milestones, violation types and EPA's complete case summaries, plus inspections and informal actions.

Create a free account

Capital improvement projects in Moline

Moline's capital improvement plan lists 59 water, sewer and wastewater line items worth $82M starting 2025–2027. The largest budgeted items are shown here.

All water and sewer capital projects in Moline →

ProjectBudgetYears
South Slope Construction (and Engineering)$56,000,0002025–2027
Lead Service Replacements$9,000,0002025–2027
Water Treatment Plant Improvement Planning Study Recommendation$2,250,0002025–2027
Per- and Polyfluoroalkyl Substances Powdered Activated Carbon Installation$2,100,0002026–2026
Sewer Lining$1,400,0002025–2027

Full project details — scope, funding source, engineering consultant and the decision-makers behind each project — are available in Klarifi, along with similar wastewater capital projects in other cities.

See full project details

Find similar projects in other cities →

Key contacts

5 verified contacts for North Slope Treatment Plant, with validated emails and direct phone numbers.

Unlock 5 verified contacts (2 more than shown)

Names, validated emails and direct phone numbers for decision-makers at North Slope Treatment Plant, plus the full compliance history and discharge data.

Try Klarifi free

Nearby wastewater treatment plants in Illinois

Moline South Treatment Plant

Moline · 4 mi away

3.64 MGD

Milan STP

Milan · 5 mi away

0.77 MGD

East Moline Wastewater

East Moline · 6 mi away

4.16 MGD

0.05 MGD

0.3 MGD

0.46 MGD

Reynolds Stp, Village Of

Reynolds · 14 mi away

0.14 MGD

Sherrard Stp, Village Of

Sherrard · 14 mi away

0.15 MGD

North Slope Treatment Plant: frequently asked questions

Sources and methodology

Flow, permit and violation figures come from the EPA's ICIS-NPDES discharge monitoring records. Population served comes from the Clean Watersheds Needs Survey 2022. Treatment structures are identified by Klarifi's review of aerial imagery, and capital improvement projects are extracted from published municipal budget documents. Violations are counted over the last three years of monitoring reports.

Data refreshed October 26, 2026; facility record last updated May 17, 2025.

Wastewater terms: POTW · MGD · NPDES permit · Inflow and infiltration · Significant industrial user · WWTP · all terms


Try Klarifi for free

Create your own trial account and explore how Klarifi can help you.

Try for free