Klarifi Logo
Try for freeLog in
Klarifi Logo

Pittsfield Wastewater Treatment Facility

Pittsfield, MA · Berkshire County · Publicly Owned Treatment Works

Average flow
7 MGD
Design flow
17 MGD
NPDES permit
MA0101681
Effective
Permit expires
October 2026
Population served
48,150
CWNS 2022

Pittsfield Wastewater Treatment Facility is a publicly owned wastewater treatment works in Pittsfield, Berkshire County, Massachusetts treating an average of 7 million gallons per day against a permitted design capacity of 17 MGD, serving about 48,150 residents. Treatment on site includes clarifiers, carrousels / oxidation ditches, biogas silos, biogas balloons, biological n removal and other unit processes. It discharges under NPDES permit MA0101681 (effective), which expires in October 2026, with 84 recorded violations in the last three years.

Treatment technology

Treatment structures identified at this facility. Exact unit counts are available in Klarifi.

Clarifiers

Unlock

Carrousels / oxidation ditches

Unlock

Biogas silos

Unlock

Biogas balloons

Unlock

Biological N removal

unit process

Biosolids Anaerobic Digestion with Energy Recovery

unit process

Biosolids Thickening

unit process

Chemical Addition, Polymer

unit process

Chemical P Removal

unit process

Dechlorination

unit process

Disinfection, chlorine/ chloramine

unit process

Flow Equalization

unit process

Primary Clarification or Sedimentation

unit process

Screening

unit process

Suspended Growth, Aerobic

unit process

Unlock exact unit counts →

Compliance snapshot (last 3 years)

Total violations
84
Effluent violations
26

Based on NPDES Discharge Monitoring Reports. Full violation history, parameters and discharge data available in the Klarifi platform.

Capital improvement projects in Pittsfield

Pittsfield's capital improvement plan lists 19 water, sewer and wastewater line items worth $19M starting 2026–2029. The largest budgeted items are shown here.

All water and sewer capital projects in Pittsfield

ProjectBudgetYears
WWTP Raw Sewage Pump Replacement$4,300,0002028–2028
CHP - Supplemental$2,800,0002026–2026
WWTP Switchgear$2,800,0002026–2026
WWTP Road Repairs$2,300,0002027–2027
WWTP Aeration Automated Valves (EPA Grant)$1,572,5982026–2026

Full project details — scope, funding source, engineering consultant and the decision-makers behind each project — are available in Klarifi, along with similar wastewater capital projects in other cities.

See full project details

Find similar projects in other cities →

Key contacts

5 verified contacts for Pittsfield Wastewater Treatment Facility, with validated emails and direct phone numbers.

Unlock 5 verified contacts (2 more than shown)

Names, validated emails and direct phone numbers for decision-makers at Pittsfield Wastewater Treatment Facility, plus the full compliance history and discharge data.

Try Klarifi free

Nearby wastewater treatment plants in Massachusetts

0.3 MGD

0.47 MGD

West Stockbridge W W T F

West Stockbridge · 8 mi away

0.009 MGD

Stockbridge W W T P

Stockbridge · 9 mi away

0.1 MGD

Hoosic Wastwater Treament Plant

Williamstown · 22 mi away

2.04 MGD

Huntington W W T P

Huntington · 22 mi away

0.03 MGD

0.04 MGD

Monroe W W T F

Monroe Bridge · 27 mi away

0.0027 MGD

Pittsfield Wastewater Treatment Facility: frequently asked questions

Sources and methodology

Flow, permit and violation figures come from the EPA's ICIS-NPDES discharge monitoring records. Population served comes from the Clean Watersheds Needs Survey 2022. Treatment structures are identified by Klarifi's review of aerial imagery, and capital improvement projects are extracted from published municipal budget documents. Violations are counted over the last three years of monitoring reports.

Data refreshed September 11, 2026; facility record last updated March 16, 2025.


Try Klarifi for free

Create your own trial account and explore how Klarifi can help you.

Try for free