Juneau, Alaska: water and wastewater capital improvement projects

113 line items · $431M · starting 2026–2031 · 1 plan

Juneau's published capital plans list 113 water, sewer and wastewater line items with a combined planning budget of $431M, of which 42 items worth $236M sit in the wastewater and sewer departments. The largest single item is MWWTP Augmentation / Replacement at $87M (2031). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Juneau

The 10 largest water, sewer and wastewater line items in Juneau’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1MWWTP Augmentation / ReplacementWastewater$87M2031
2MWWTP Conversion to AGSWastewater$25M2031
3Additional Street ReconstructionsWater DistributionWater mains and distribution$19M2027–2031
4S Franklin - Taku Smokeries to Baranof replacement or slip lineWater Distribution$11M2031
5WW Collections Operations ShopWastewater$10M2027–2031
6MWWTP Treatment Upgrades - SBR Tank Rehab/Full Floor AerationWastewaterAeration and blowers$10M2027–2029
7North Douglas Waterline - 4000 block to Bonnie BraeWater DistributionWater mains and distribution$9M2029–2030
8Water Utility ShopWater Supply$9M2029–2031
9Fritz Cove Waterline ReplacementWater DistributionWater mains and distribution$8M2027–2031
10Lift Station UpgradesSewerLift stations$8M2027–2031

103 more line items in Juneau, with descriptions and contacts

Klarifi holds every Juneau line item with its description, the page it appears on and the source document, plus 9 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

2026

$8M

15 items

2027

$148M

53 items

2028

$26M

13 items

2029

$29M

8 items

2030

$42M

9 items

2031

$177M

15 items

By department

Line items and planning budgets by department, Juneau.
DepartmentLine itemsBudgetShare
Wastewater29$206M48%
Sewer13$30M7%
Water Supply21$55M13%
Water Distribution50$139M32%

Project types in Juneau's plan

Wastewater treatment plants in Juneau

2 publicly owned treatment plants in Juneau with 71 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
Mendenhall Valley WWTP2.44AK002295159
Auke Bay Wastewater Treatment Facility0.08AKG57200412

Other Alaska cities with capital plans

Juneau capital plan questions

Sources and methodology

Budgets and years are as published in Juneau’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2026–2031 (113 line items).

Data refreshed September 11, 2026.