Klarifi Logo
Try for freeLog in
Klarifi Logo

Shakopee, Minnesota: water and wastewater capital improvement projects

28 line items · $14M · starting 2026–2030 · 1 plan

Shakopee's published capital plans list 28 water, sewer and wastewater line items with a combined planning budget of $14M, of which 28 items worth $14M sit in the wastewater and sewer departments. The largest single item is Trunk Sewer Extensions at $3M (2025–2039). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Shakopee

The 10 largest water, sewer and wastewater line items in Shakopee’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Trunk Sewer ExtensionsSewerForce mains and interceptors$3M2025–2039
2L16 Dual Forcemain ImprovementsSewerForce mains and interceptors$3M2025–2029
3L16 Forcemain LiningSewerForce mains and interceptors$2M2030
4West End (High Bluff) Lift StationSewerLift stations$1M2030
5Jetter Truck (Freightliner)SewerVehicles and equipment$626K2037
6Lift Station 16 RehabSewerLift stations$515K2035
7SCADA System UpgradeSewerSCADA, controls and instrumentation$500K2030
8Sewer Jetter ReplacementSewerSewer rehabilitation and I&I$450K2028
9CSAH 83/TH 169 Trunk Sewer Crossing ExpansionSewerForce mains and interceptors$410K2034
10Cured In Place Sewer Pipe LiningSewerSewer rehabilitation and I&I$400K2034

18 more line items in Shakopee, with descriptions and contacts

Klarifi holds every Shakopee line item with its description, the page it appears on and the source document, plus 3 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

Before 2026

$6M

4 items

2026

$123K

1 items

2028

$456K

2 items

2029

$187K

1 items

2030

$4M

10 items

2032 and later

$3M

10 items

By department

Line items and planning budgets by department, Shakopee.
DepartmentLine itemsBudgetShare
Sewer28$14M100%

Wastewater treatment plants in Shakopee

1 publicly owned treatment plant in Shakopee. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
Blue Lake Wastewater Treatment Plant26.54MN00298820

Other Minnesota cities with capital plans

Shakopee capital plan questions

Sources and methodology

Budgets and years are as published in Shakopee’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2025–2029 (28 line items).

Data refreshed September 11, 2026.

Try Klarifi for free

Create your own trial account and explore how Klarifi can help you.

Try for free