16 line items · $23M · 1 plan
Lancaster's published capital plans list 16 water, sewer and wastewater line items with a combined planning budget of $23M, of which 11 items worth $11M sit in the wastewater and sewer departments. The largest single item is WWTP Optimization Project at $8M (2025–2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | WWTP Optimization Project | Wastewater | Wastewater treatment plant upgrades | $8M | 2025–2026 |
| 2 | S Main Street Water Line | Water Distribution | Water mains and distribution | $4M | 2025–2026 |
| 3 | W. Meeting Street Water Project | Water Distribution | Water mains and distribution | $4M | 2025–2026 |
| 4 | Water Meter Replcaement | Water Distribution | Meters and AMI | $3M | 2025–2026 |
| 5 | Bypass Pump Station Replacement | Sewer | Pump stations | $2M | 2025–2026 |
| 6 | Jet-Vac | Sewer | Vehicles and equipment | $568K | 2025–2026 |
| 7 | 18 Ton Boom Truck | Water Distribution | Vehicles and equipment | $301K | 2025–2026 |
| 8 | WWTP Roof | Wastewater | Wastewater treatment plant upgrades | $190K | 2025–2026 |
| 9 | New RAS/WAS Pumps Clarifier 3 | Wastewater | Clarifiers and settling | $128K | 2025–2026 |
| 10 | WWTP Trunk Lines | Sewer | Force mains and interceptors | $100K | 2025–2026 |
6 more line items in Lancaster, with descriptions and contacts
Klarifi holds every Lancaster line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$23M
16 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 4 | $9M | 38% |
| Sewer | 7 | $3M | 12% |
| Water Distribution | 5 | $12M | 51% |
No publicly owned treatment plant is recorded under Lancaster in the facility directory; the city may be served by a regional plant listed under another municipality. Browse all plants in South Carolina.
Sources and methodology
Budgets and years are as published in Lancaster’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2026 (16 line items).