Tidwell Timbers WWTP

10545 Tidwell Road, Houston, TX 77078 · Harris County · Publicly Owned Treatment Works

Average flow
0.42 MGD
Design flow
0.49 MGD
NPDES permit
TX0101460
Effective
Permit expires
December 2027
Population served
9,760
CWNS 2022

Tidwell Timbers WWTP is a publicly owned wastewater treatment works in Houston, Harris County, Texas treating an average of 0.42 million gallons per day against a permitted design capacity of 0.49 MGD, serving about 9,760 residents. It discharges under NPDES permit TX0101460 (effective), which expires in December 2027, with 7 recorded violations in the last three years. EPA has recorded 1 formal enforcement action naming the plant, the latest in April 2021.

Treatment technology

One treatment structure or unit process identified at Tidwell Timbers WWTP.

Available with a free Klarifi account

See the full treatment train at Tidwell Timbers WWTP: structures, unit processes and planned upgrades, with exact unit counts.

Create a free account

Compliance snapshot (last 3 years)

Total violations
7
Effluent violations
7

Based on NPDES Discharge Monitoring Reports. Full violation history, parameters and discharge data available in the Klarifi platform.

EPA enforcement history

Federal civil enforcement cases, compliance inspections and informal actions recorded for Tidwell Timbers WWTP in EPA's ICIS system.

Formal actions
1
0 since FY2020
Penalties assessed
$4.4M
all cases
Compliance actions
$2,000M
required by EPA orders
EPA inspections
0
none on record

Latest case · Apr 2021

Houston, City of

Judicial case · CWA, NPDES Permit Violations · Final Order With Penalty · Penalty $4.4M · Compliance actions $2,000M · The case also names 35 other plants, and its amounts cover all of them

EPA's description of the case:

“City of Houston was issued the Consent Decree for both permit effluent violations and Sanitary Sewer Overflows.”

Source: EPA ECHO, civil enforcement case 06-2010-1780.

Full case history with a free Klarifi account

Every action against Tidwell Timbers WWTP with dates, milestones, violation types and EPA's complete case summaries, plus inspections and informal actions.

Create a free account

Capital improvement projects in Houston

Houston's capital improvement plan lists 22 water, sewer and wastewater line items worth $1.3B starting 2025–2025. The largest budgeted items are shown here.

All water and sewer capital projects in Houston →

ProjectBudgetYears
Wastewater Treatment Plant Improvements$353,943,2002025–2025
Wastewater Treatment Plant Consolidation$166,807,0002025–2025
Surface Water Transmission Program$132,740,1442025–2025
Neighborhood Sewer Rehab Program$96,000,0002025–2025
Pump Station Program$87,851,6002025–2025

Full project details — scope, funding source, engineering consultant and the decision-makers behind each project — are available in Klarifi, along with similar wastewater capital projects in other cities.

See full project details

Find similar projects in other cities →

Key contacts

39 verified contacts for Tidwell Timbers WWTP, with validated emails and direct phone numbers.

Unlock 39 verified contacts (36 more than shown)

Names, validated emails and direct phone numbers for decision-makers at Tidwell Timbers WWTP, plus the full compliance history and discharge data.

Try Klarifi free

Nearby wastewater treatment plants in Texas

Greenwood Ud - WWTP

Houston · 1 mi away

1.62 MGD

Kindred Ii Lp WWTF

Houston · 2 mi away

0.45 MGD

Greensbrook WWTP

Houston · 3 mi away

0.64 MGD

Freshwater Supply District 23

Houston · 3 mi away

13.57 MGD

Hunterwood Apartments WWTF

Houston · 3 mi away

—

Royalwood South WWTP

Houston · 3 mi away

0.27 MGD

Harris County Mud 8 WWTP

Houston · 5 mi away

0.58 MGD

Northeast WWTP

Houston · 5 mi away

13.71 MGD

Tidwell Timbers WWTP: frequently asked questions

Sources and methodology

Flow, permit and violation figures come from the EPA's ICIS-NPDES discharge monitoring records. Population served comes from the Clean Watersheds Needs Survey 2022. Treatment structures are identified by Klarifi's review of aerial imagery, and capital improvement projects are extracted from published municipal budget documents. Violations are counted over the last three years of monitoring reports.

Data refreshed October 26, 2026; facility record last updated May 29, 2025.

Wastewater terms: POTW · MGD · NPDES permit · Inflow and infiltration · Equalization tank · Centrate · all terms


Try Klarifi for free

Create your own trial account and explore how Klarifi can help you.

Try for free