19 line items · $2M · starting 2026–2027 · 1 plan
Poolesville's published capital plans list 19 water, sewer and wastewater line items with a combined planning budget of $2M, of which 13 items worth $773K sit in the wastewater and sewer departments. The largest single item is PFAS Remediation at $500K (2025–2029). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | PFAS Remediation | Water Supply | PFAS treatment | $500K | 2025–2029 |
| 2 | Equip Replace/Major Rebuild | Water Supply | — | $200K | 2025–2029 |
| 3 | Basin Recoating | Wastewater | Buildings, HVAC and site work | $180K | 2025–2027 |
| 4 | Alpha Media | Water Supply | — | $175K | 2025–2029 |
| 5 | Unidentified W&S Equipment | Sewer | Vehicles and equipment | $150K | 2025–2029 |
| 6 | 1- Ton Utility Truck | Wastewater | Vehicles and equipment | $135K | 2025–2029 |
| 7 | Water Meter Replacement | Water Distribution | Meters and AMI | $100K | 2025–2029 |
| 8 | Generator | Wastewater | Generators, power and electrical | $90K | 2025–2026 |
| 9 | Paint WWTP | Wastewater | Wastewater treatment plant upgrades | $75K | 2025–2027 |
| 10 | Basin/wetwell pump-out/Repair | Wastewater | Pump stations | $60K | 2026–2028 |
9 more line items in Poolesville, with descriptions and contacts
Klarifi holds every Poolesville line item with its description, the page it appears on and the source document, plus 4 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$2M
16 items
2026
$64K
2 items
2027
$30K
1 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 10 | $596K | 33% |
| Sewer | 3 | $177K | 10% |
| Water Supply | 5 | $955K | 52% |
| Water Distribution | 1 | $100K | 5% |
1 publicly owned treatment plant in Poolesville with 6 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Poolesville WWTP | 0.34 | MD0023001 | 6 |
Sources and methodology
Budgets and years are as published in Poolesville’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2024–2029 (19 line items).
Data refreshed September 11, 2026.