South Burlington, Vermont: water and wastewater capital improvement projects

33 line items · $48M · starting 2026–2031 · 1 plan

South Burlington's published capital plans list 33 water, sewer and wastewater line items with a combined planning budget of $48M, of which 23 items worth $38M sit in the wastewater and sewer departments. The largest single item is Bartlett Bay 2025 Upgrade at $13M (2026–2035). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in South Burlington

The 10 largest water, sewer and wastewater line items in South Burlington’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Bartlett Bay 2025 UpgradeWastewaterWastewater treatment plant upgrades$13M2026–2035
2Airport Parkway 2011 UpgradeWastewaterWastewater treatment plant upgrades$8M2026–2033
3High Service Storage TankWater SupplyStorage tanks and reservoirs$4M2026–2035
4Queen City Park Pump StationsSewerPump stations$3M2026–2035
5Pump Station RefurbishmentSewerPump stations$3M2026–2035
6Valve and Hydrant Replacement Pre-PavingWater DistributionWater mains and distribution$2M2027–2035
7Hinesburg Road Pump StationSewerPump stations$2M2028–2035
8FleetWastewaterVehicles and equipment$1M2026–2033
9Airport Parkway Solids HandlingWastewaterBiosolids, sludge and dewatering$1M2026–2035
10South Spear Street Water LineWater DistributionWater mains and distribution$1M2027–2035

23 more line items in South Burlington, with descriptions and contacts

Klarifi holds every South Burlington line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

2026

$39M

18 items

2027

$4M

5 items

2028

$2M

3 items

2029

$1M

2 items

2031

$352K

2 items

2032 and later

$250K

3 items

By department

Line items and planning budgets by department, South Burlington.
DepartmentLine itemsBudgetShare
Wastewater12$25M52%
Sewer11$13M27%
Water Supply1$4M7%
Water Distribution9$6M13%

Project types in South Burlington's plan

Wastewater treatment plants in South Burlington

No publicly owned treatment plant is recorded under South Burlington in the facility directory; the city may be served by a regional plant listed under another municipality. Browse all plants in Vermont.

South Burlington capital plan questions

Sources and methodology

Budgets and years are as published in South Burlington’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2026–2035 (33 line items).

Data refreshed September 11, 2026.