11 line items · $993M · starting 2026–2027 · 1 plan
Chesterfield's published capital plans list 11 water, sewer and wastewater line items with a combined planning budget of $993M, of which 4 items worth $289M sit in the wastewater and sewer departments. The largest single item is Appomattox River Water Treatment Plant at $394M (2026–2027). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Appomattox River Water Treatment Plant | Water Supply | Water treatment plants | $394M | 2026–2027 |
| 2 | Wastewater Plants | Wastewater | Wastewater treatment plant upgrades | $200M | 2026–2029 |
| 3 | Waterlines | Water Distribution | Water mains and distribution | $118M | 2026–2030 |
| 4 | Water Pump Stations | Water Supply | Pump stations | $63M | 2026–2030 |
| 5 | Wastewater Pump Stations | Wastewater | Pump stations | $55M | 2026–2029 |
| 6 | Addison-Evans Water Treatment Plant | Water Supply | Water treatment plants | $40M | 2026–2029 |
| 7 | Water Tanks | Water Supply | Storage tanks and reservoirs | $39M | 2026–2030 |
| 8 | Wastewater Lines | Wastewater | Water mains and distribution | $30M | 2027–2029 |
| 9 | Richmond Capacity | Water Supply | Headworks, screening and grit | $26M | 2027–2029 |
| 10 | Technology and Other Projects | Water Supply | Buildings, HVAC and site work | $25M | 2026–2029 |
1 more line items in Chesterfield, with descriptions and contacts
Klarifi holds every Chesterfield line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.
2026
$937M
9 items
2027
$56M
2 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 4 | $289M | 29% |
| Water Supply | 6 | $587M | 59% |
| Water Distribution | 1 | $118M | 12% |
No publicly owned treatment plant is recorded under Chesterfield in the facility directory; the city may be served by a regional plant listed under another municipality. Browse all plants in Virginia.
Sources and methodology
Budgets and years are as published in Chesterfield’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2026–2030 (11 line items).