Channahon, Illinois: water and wastewater capital improvement projects

16 line items · $79M · starting 2026–2030 · 1 plan

Channahon's published capital plans list 16 water, sewer and wastewater line items with a combined planning budget of $79M, of which 1 items worth $49M sit in the wastewater and sewer departments. The largest single item is Far West Side Waste Water Treatment Plant at $49M (2026–2030). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Channahon

The 10 largest water, sewer and wastewater line items in Channahon’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Far West Side Waste Water Treatment PlantWastewaterWastewater treatment plant upgrades$49M2026–2030
2Construction of Primary & Secondary Delivery Point - Related to the Lake Michigan Water CommissionWater Distribution$10M2029–2030
3Water System Reinforcement for Lake Michigan Water (1 Million Gallon Storage Tank)Water DistributionStorage tanks and reservoirs$7M2026–2028
4Watermain Reinforcement for Lake Michigan Water (12-Inch Pipe Along US Rt. 6)Water DistributionWater mains and distribution$3M2026
5Watermain Reinforcement for Lake Michigan Water (12-Inch Pipe Along Blackberry Road)Water DistributionWater mains and distribution$2M2026
6Watermain Reinforcement for Lake Michigan Water (16-Inch Pipe Along US Rt. 6)Water DistributionWater mains and distribution$2M2026
7Construction of Watermain Reinforcement for Lake Michigan Water (12-inch pipe along Ridge Road)Water DistributionWater mains and distribution$2M2028
8Water Meter Change OutWater DistributionMeters and AMI$2M2029–2030
9Tower #4 RehabilitationWater DistributionWells and groundwater$740K2030
10Design Primary & Secondary Delivery Point - Related to the Lake Michigan Water CommissionWater Distribution$540K2028

6 more line items in Channahon, with descriptions and contacts

Klarifi holds every Channahon line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

2026

$64M

8 items

2027

$669K

3 items

2028

$2M

2 items

2029

$11M

2 items

2030

$740K

1 items

By department

Line items and planning budgets by department, Channahon.
DepartmentLine itemsBudgetShare
Wastewater1$49M63%
Water Supply2$155K0%
Water Distribution13$29M37%

Wastewater treatment plants in Channahon

No publicly owned treatment plant is recorded under Channahon in the facility directory; the city may be served by a regional plant listed under another municipality. Browse all plants in Illinois.

Other Illinois cities with capital plans

Channahon capital plan questions

Sources and methodology

Budgets and years are as published in Channahon’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2026–2030 (16 line items).

Data refreshed September 11, 2026.