15 line items · $71M · starting 2026–2027 · 1 plan
Fredericksburg's published capital plans list 15 water, sewer and wastewater line items with a combined planning budget of $71M, of which 8 items worth $39M sit in the wastewater and sewer departments. The largest single item is Sanitary Sewer Interceptors at $28M (2025–2029). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Sanitary Sewer Interceptors | Wastewater | Force mains and interceptors | $28M | 2025–2029 |
| 2 | Spotsylvania Shared Water Project | Water Distribution | Water treatment plants | $24M | 2025 |
| 3 | NPS / Farrell Ln Sewer Main Replacement | Wastewater | Sewer rehabilitation and I&I | $3M | 2027–2029 |
| 4 | Internal System Improvements | Water Distribution | Water mains and distribution | $3M | 2025–2029 |
| 5 | Sanitary Sewer System Improvements | Wastewater | Sewer rehabilitation and I&I | $3M | 2025–2029 |
| 6 | Annual Sewer Cleaning & Inspection | Wastewater | Sewer rehabilitation and I&I | $3M | 2025–2029 |
| 7 | Main St. Pump Station Force Main Replacement | Water Distribution | Pump stations | $2M | 2026 |
| 8 | Telegraph Hill Loop | Water Distribution | Water mains and distribution | $1M | 2026–2027 |
| 9 | Upper Prince Anne Sewer Replacement | Wastewater | Sewer rehabilitation and I&I | $1M | 2026–2027 |
| 10 | WWTP Capital Maintenance | Wastewater | Wastewater treatment plant upgrades | $650K | 2025 |
5 more line items in Fredericksburg, with descriptions and contacts
Klarifi holds every Fredericksburg line item with its description, the page it appears on and the source document, plus 2 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$63M
9 items
2026
$5M
5 items
2027
$3M
1 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 8 | $39M | 55% |
| Water Distribution | 7 | $32M | 45% |
2 publicly owned treatment plants in Fredericksburg with 14 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Fredericksburg Wastewater Treatment Facility | 2.33 | VAL025127 | 12 |
| Fmc Wastewater Treatment Plant | 2.02 | VAL068110 | 2 |
Sources and methodology
Budgets and years are as published in Fredericksburg’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2029 (15 line items).
Data refreshed September 11, 2026.