32 line items · $61M · starting 2026–2027 · 1 plan
Pacifica's published capital plans list 32 water, sewer and wastewater line items with a combined planning budget of $61M, of which 32 items worth $61M sit in the wastewater and sewer departments. The largest single item is Collection System Rehabilitation & Replacement Projects: Vallemar and Rockaway Beach Avenue at $18M (2025–2028). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Collection System Rehabilitation & Replacement Projects: Vallemar and Rockaway Beach Avenue | Sewer | Sewer rehabilitation and I&I | $18M | 2025–2028 |
| 2 | CCWRP Headworks Feasibility and Improvements | Wastewater | Headworks, screening and grit | $8M | 2024–2027 |
| 3 | Ultraviolet Disinfection System Upgrade | Wastewater | Disinfection and UV | $7M | 2024–2026 |
| 4 | Lower Linda Mar Rehabilitation and Repair Project (Renamed) | Sewer | Sewer rehabilitation and I&I | $6M | 2024–2025 |
| 5 | Relocation of Sewer Mainline at SF RV Park | Sewer | Sewer rehabilitation and I&I | $4M | 2026–2029 |
| 6 | Sharp Park Pump Station R&R Project (Formerly Sharp Park PS Facility Improvements Project) | Sewer | Pump stations | $3M | 2024–2028 |
| 7 | Crespi to Anza Sewer Replacement Project | Sewer | Sewer rehabilitation and I&I | $2M | 2025–2027 |
| 8 | CCWRP Electrical Condition Assessment and Improvements | Wastewater | Generators, power and electrical | $2M | 2024–2027 |
| 9 | Linda Mar Peralta Project | Sewer | Sewer rehabilitation and I&I | $2M | 2024–2025 |
| 10 | Linda Mar Pump Station R&R Project (Formerly LMPS Upgrade C004B) | Sewer | Pump stations | $1M | 2024–2026 |
22 more line items in Pacifica, with descriptions and contacts
Klarifi holds every Pacifica line item with its description, the page it appears on and the source document, plus 15 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$56M
26 items
2026
$4M
3 items
2027
$440K
3 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 20 | $22M | 36% |
| Sewer | 12 | $39M | 64% |
1 publicly owned treatment plant in Pacifica with 4 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Calera Creek Wrp | 1.91 | CA0038776 | 4 |
Sources and methodology
Budgets and years are as published in Pacifica’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2024–2029 (32 line items).
Data refreshed September 11, 2026.