California water and wastewater capital improvement plans

1,103 planned projects · $5.1B · 40 cities · 41 plans

The 41 capital improvement plans and adopted budgets Klarifi has extracted for California list 1,103 water, sewer and wastewater line items with a combined planning budget of $5.1B across 40 cities. Ventura has the largest plan at $824M. Each city page lists its largest projects with budgets and years, links the source document and the city's treatment plants.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

Wastewater plants in CaliforniaCalifornia NPDES permits →

Cities in California with water and sewer capital plans

California cities ranked by the combined planning budget of their water, sewer and wastewater line items.
#CityLine itemsBudgetPlans
1Ventura22$824M1
2Oceanside51$463M1
3Santa Barbara19$450M1
4Carlsbad53$369M1
5Santa Cruz39$312M1
6Oxnard25$245M1
7Corona40$240M1
8Sacramento28$216M1
9Riverside21$200M1
10Merced66$176M1
11San Luis Obispo115$170M1
12Windsor20$163M1
13Watsonville30$154M1
14Stockton26$98M1
15Simi Valley77$92M1
16Chino27$90M1
17Pismo Beach32$89M1
18Fort Bragg20$79M1
19Brentwood22$74M1
20Long Beach18$70M2
21Manteca27$67M1
22Pacifica32$61M1
23Richmond9$52M1
24Eureka17$49M1
25Santa Rosa14$39M1
26Nevada City29$38M1
27Lompoc23$35M1
28Galt14$30M1
29Morro Bay8$29M1
30Fountain Valley15$28M1
31Woodland15$16M1
32Fortuna15$15M1
33Beaumont22$14M1
34Bear Valley45$13M1
35Pico Rivera3$12M1
36Yuba City22$7M1
37San Francisco31$6M1
38Willows9$4M1

Planned spend by start year

Before 2026

$3.7B

610 items

2026

$600M

196 items

2027

$336M

121 items

2028

$177M

60 items

2029

$144M

62 items

2030

$97M

24 items

2031

$4M

11 items

2032 and later

$54M

19 items

By department

Line items and planning budgets by utility department, California.
DepartmentLine itemsBudgetShare
Wastewater261$1.4B28%
Sewer299$1.1B22%
Water Supply277$1.3B26%
Water Distribution266$1.2B23%

Project types in California

Water mains and distribution · 191 · $1.0BSewer rehabilitation and I&I · 158 · $463MWastewater treatment plant upgrades · 58 · $434MDisinfection and UV · 17 · $333MPump stations · 65 · $312MWater treatment plants · 28 · $244MLift stations · 37 · $219MBiosolids, sludge and dewatering · 30 · $219MStormwater and flood resilience · 13 · $181MWells and groundwater · 46 · $180M

The largest planned projects in California

The ten largest water, sewer and wastewater line items in California plans by planning budget.
#ProjectCityTypeBudgetYears
1Wastewater Plant - Membrane Bio-Reactor/UV Disinfection (VWP)3Ventura, CADisinfection and UV$302M2025–2031
2Wastewater Plant - Advanced Purification Facility (VWP)Ventura, CAWastewater treatment plant upgrades$200M2025–2031
3Encina Capital Projects (EWPCF)Carlsbad, CA$160M2024–2039
4Vic Trace Reservoir Replacement and Resiliency ProjectSanta Barbara, CAStormwater and flood resilience$125M2025–2030
5Outfall Pump Station and Temporary Facilities (VWP)Ventura, CAPump stations$116M2025–2026
6Water Main Replacement ProgramSanta Barbara, CAWater mains and distribution$111M2025–2031
7Oxnard Plain Basin Storage (VWP)Ventura, CA$82M2025–2031
8Buccaneer Lift StationOceanside, CALift stations$76M2024–2028
9GHWTP Facilities Improvement ProjectSanta Cruz, CAWater treatment plants$68M2026–2030
10Main Replacements ProgramRiverside, CAWater mains and distribution$62M2024–2029

All 1,103 California line items in Klarifi

Every project with its description, page reference and source document, filterable by city, department, type, budget and year, linked to the plants and decision-makers in each city.

Start a free trial

California capital plan questions

Sources and methodology

Budgets and years are as published in each city’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Data refreshed September 11, 2026.