22 line items · $74M · starting 2027–2028 · 1 plan
Brentwood's published capital plans list 22 water, sewer and wastewater line items with a combined planning budget of $74M, of which 11 items worth $54M sit in the wastewater and sewer departments. The largest single item is Wastewater Treatment Plant Expansion - Phase II at $30M (2025–2027). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Wastewater Treatment Plant Expansion - Phase II | Wastewater | Wastewater treatment plant upgrades | $30M | 2025–2027 |
| 2 | Brentwood Manor Water and Wastewater Rehabilitation | Water Distribution | Sewer rehabilitation and I&I | $6M | 2025–2026 |
| 3 | Pump Station 2.4 Installation | Water Distribution | Pump stations | $4M | 2025–2026 |
| 4 | Wastewater Treatment Plant Tertiary Filter Expansion | Wastewater | Membranes and filtration | $4M | 2028–2029 |
| 5 | Brentwood Boulevard Wastewater Rehabilitation | Sewer | Membranes and filtration | $4M | 2025–2026 |
| 6 | Wastewater Treatment Plant Secondary Clarifier Replacement | Wastewater | Clarifiers and settling | $4M | 2028–2029 |
| 7 | Wastewater Treatment Plant Headworks Rehabilitation | Wastewater | Headworks, screening and grit | $3M | 2025–2028 |
| 8 | Water and Wastewater Laboratory | Wastewater | Buildings, HVAC and site work | $3M | 2025–2026 |
| 9 | Water and Wastewater SCADA System Upgrade | Wastewater | SCADA, controls and instrumentation | $2M | 2025–2027 |
| 10 | On-Site Chlorine Generation System Upgrade | Water Supply | Disinfection and UV | $2M | 2025–2026 |
12 more line items in Brentwood, with descriptions and contacts
Klarifi holds every Brentwood line item with its description, the page it appears on and the source document, plus 2 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$64M
19 items
2027
$2M
1 items
2028
$8M
2 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 6 | $46M | 62% |
| Sewer | 5 | $8M | 11% |
| Water Supply | 2 | $3M | 4% |
| Water Distribution | 9 | $17M | 23% |
1 publicly owned treatment plant in Brentwood with 17 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Brentwood Wastewater Treatment Plant | 1.46 | CA0082660 | 17 |
Sources and methodology
Budgets and years are as published in Brentwood’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2030 (22 line items).
Data refreshed September 11, 2026.