25 line items · $245M · starting 2026–2029 · 1 plan
Oxnard's published capital plans list 25 water, sewer and wastewater line items with a combined planning budget of $245M, of which 10 items worth $106M sit in the wastewater and sewer departments. The largest single item is Wastewater OWTP: Primary Clarifiers and Activated Sludge Improvements at $43M (2025–2027). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Wastewater OWTP: Primary Clarifiers and Activated Sludge Improvements | Wastewater | Biosolids, sludge and dewatering | $43M | 2025–2027 |
| 2 | Water Distribution: Oxnard Conduit Replacement Project | Water Distribution | Water mains and distribution | $42M | 2025–2028 |
| 3 | Recycled Water: AWPF Improvements and Expansion | Water Supply | Water reuse and reclaimed water | $33M | 2025–2029 |
| 4 | Water Distribution: Kamala Park Neighborhood Cast Iron Pipe Replacement | Water Distribution | Water mains and distribution | $27M | 2025–2027 |
| 5 | Wastewater OWTP: Digester/Cogeneration Improvements | Wastewater | Anaerobic digesters and biogas | $17M | 2025–2029 |
| 6 | Wastewater OWTP: Interstage Pump Station and Bio-tower Demolition | Wastewater | Pump stations | $13M | 2025–2029 |
| 7 | Water Distribution: Hobson Park East Neighborhood Cast Iron Pipe Replacement | Water Distribution | Water mains and distribution | $12M | 2025–2027 |
| 8 | Wastewater OWTP: Maintenance Office Building, Machine Shop, and Storage | Wastewater | Buildings, HVAC and site work | $8M | 2026–2027 |
| 9 | Wastewater Collection: Lift Station Improvements | Wastewater | Lift stations | $8M | 2025–2027 |
| 10 | Water Production: Groundwater Desalter Improvement Project | Water Supply | Water treatment plants | $8M | 2025–2026 |
15 more line items in Oxnard, with descriptions and contacts
Klarifi holds every Oxnard line item with its description, the page it appears on and the source document, plus 2 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$219M
16 items
2026
$14M
3 items
2027
$9M
4 items
2028
$2M
1 items
2029
$2M
1 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 8 | $99M | 40% |
| Sewer | 2 | $7M | 3% |
| Water Supply | 11 | $54M | 22% |
| Water Distribution | 4 | $86M | 35% |
1 publicly owned treatment plant in Oxnard with 137 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Oxnard Wastewater Treatment Plant (owtp) | 16.6 | CAL054097 | 137 |
Sources and methodology
Budgets and years are as published in Oxnard’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2029 (25 line items).
Data refreshed September 11, 2026.