77 line items · $92M · starting 2026–2029 · 1 plan
Simi Valley's published capital plans list 77 water, sewer and wastewater line items with a combined planning budget of $92M, of which 37 items worth $68M sit in the wastewater and sewer departments. The largest single item is SLR 8" to 12" Sewer Pipe Rehabilitation at $15M (2027–2030). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | SLR 8" to 12" Sewer Pipe Rehabilitation | Sewer | Sewer rehabilitation and I&I | $15M | 2027–2030 |
| 2 | MCC Replacement - Disinfection & Filters | Sewer | Disinfection and UV | $5M | 2027–2029 |
| 3 | Primary Clarifier Rehabilitation | Sewer | Clarifiers and settling | $4M | 2025–2028 |
| 4 | Plant Water System Pump Replacement | Sewer | Pump stations | $4M | 2025–2026 |
| 5 | Filter Equipment Replacement | Sewer | Membranes and filtration | $3M | 2028–2030 |
| 6 | SLR-Fifth to Sycamore | Sewer | Sewer rehabilitation and I&I | $3M | 2025–2026 |
| 7 | Chlorine Contact Basin Rehab | Sewer | Disinfection and UV | $3M | 2028–2030 |
| 8 | Tank Replacement - Flanagan | Water Supply | Storage tanks and reservoirs | $3M | 2026–2029 |
| 9 | SLR Los Angeles Ave Phase C | Sewer | Sewer rehabilitation and I&I | $3M | 2026–2027 |
| 10 | Water Line Repl - Sorrel, Buckskin, Pinto, Arabian | Water Distribution | Water mains and distribution | $2M | 2027–2029 |
67 more line items in Simi Valley, with descriptions and contacts
Klarifi holds every Simi Valley line item with its description, the page it appears on and the source document, plus 5 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$27M
25 items
2026
$17M
17 items
2027
$30M
15 items
2028
$13M
12 items
2029
$5M
8 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Sewer | 37 | $68M | 74% |
| Water Supply | 24 | $17M | 19% |
| Water Distribution | 16 | $7M | 8% |
1 publicly owned treatment plant in Simi Valley with 37 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Simi Vly Cnty Sanitation | 6.5 | CA0055221 | 37 |
Sources and methodology
Budgets and years are as published in Simi Valley’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2030 (77 line items).
Data refreshed September 11, 2026.