Stratford, Connecticut: water and wastewater capital improvement projects
Water, sewer and wastewater line items in Stratford’s published capital improvement plans and adopted budgets, with budgets, years and the source documents.
- Planned budget
- $23M
- Line items
- 12
- Wastewater and sewer
- $23M
- Starting
- 2027–2030
- Plan
- 1
Stratford's published capital plans list 12 water, sewer and wastewater line items with a combined planning budget of $23M, of which 12 items worth $23M sit in the wastewater and sewer departments. The largest single item is Sanitary Pump Station Renovations at $5M (2027–2028). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
The largest water and sewer projects in Stratford
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Sanitary Pump Station Renovations | Sewer | Pump stations | $5M | 2027–2028 |
| 2 | Oak Bluff Force main | Sewer | Force mains and interceptors | $4M | 2027–2029 |
| 3 | Broadbridge Ave sewer capacity upgrade | Sewer | Sewer rehabilitation and I&I | $3M | 2027–2030 |
| 4 | Broadbridge Avenue Force main | Sewer | Force mains and interceptors | $2M | 2030 |
| 5 | WPCA Inflow and Infiltration Investigation and Remediation Plan/Replace/Upgrade/Repair Projects | Sewer | Membranes and filtration | $2M | 2027–2030 |
| 6 | Access Rd Force main | Sewer | Force mains and interceptors | $2M | 2027–2028 |
| 7 | Short Beach Force main | Sewer | Force mains and interceptors | $1M | 2027–2030 |
| 8 | Install Sludge Centrifuge | Sewer | Biosolids, sludge and dewatering | $1M | 2027 |
| 9 | Hawley Lane Force main | Sewer | Force mains and interceptors | $1M | 2030 |
| 10 | Facility Plan update (Town share] | Sewer | — | $950K | 2029 |
Planned spend by start year
By department
| Department | Line items | Budget | Share |
|---|---|---|---|
| Sewer | 12 | $23M | 100% |
Project types in Stratford's plan
- Force mains and interceptors5 line items$11M
- Pump stations2 line items$5M
- Sewer rehabilitation and I&I2 line items$3M
- Membranes and filtration1 line items$2M
- Biosolids, sludge and dewatering1 line items$1M
Wastewater treatment plants in Stratford
1 publicly owned treatment plant in Stratford with 37 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Stratford Water Pollution Control Facility | 7.81 | CT0101036 | 37 |
Other Connecticut cities with capital plans
- $277M
- $192M
- $102M
- $18M
- $9M
- $7M
- $5M
- $2M
Stratford capital plan questions
How much is Stratford, CT planning to spend on water and sewer infrastructure?
Stratford’s published capital plans list 12 water, sewer and wastewater line items with a combined budget of $23M, of which $23M is in the wastewater and sewer departments.
What is the largest capital project in Stratford’s plan?
Sanitary Pump Station Renovations, budgeted at $5M and scheduled for 2027–2028 under the Sewer department.
When do Stratford’s water and sewer projects start?
8 projects ($19M) start in 2027 and 2 projects ($1M) start in 2029. Budgets are as published in the plan and can change at adoption.
How do I find the contacts and full project list for Stratford?
Klarifi holds every line item with its description, page reference and source document, plus 8 verified contacts at the city’s treatment plants. The public page shows the ten largest items; the full list is available with a free trial.
Try Klarifi for free
Create your own trial account and explore how Klarifi can help you.