10 line items · $2M · starting 2026–2027 · 1 plan
Gladstone's published capital plans list 10 water, sewer and wastewater line items with a combined planning budget of $2M, of which 3 items worth $413K sit in the wastewater and sewer departments. The largest single item is 4" WM Blocks 75-80-91-94 at $400K (2026–2027). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | 4" WM Blocks 75-80-91-94 | Water Supply | — | $400K | 2026–2027 |
| 2 | Upflow Clarifiers | Water Supply | Clarifiers and settling | $310K | 2027–2028 |
| 3 | GAC Filter | Water Supply | Membranes and filtration | $200K | 2025–2026 |
| 4 | UPLS Force Main | Wastewater | Force mains and interceptors | $200K | 2025–2026 |
| 5 | CIPP Collection System | Wastewater | Sewer rehabilitation and I&I | $170K | 2024–2028 |
| 6 | Plant Study | Water Supply | Planning, studies and asset management | $75K | 2026–2027 |
| 7 | HS Pumps | Water Supply | Pump stations | $45K | 2024–2025 |
| 8 | Meter Upgrades | Wastewater | Meters and AMI | $43K | 2024–2026 |
| 9 | LS Pumps | Water Supply | Pump stations | $36K | 2024–2025 |
| 10 | Filter Pumps | Water Supply | Membranes and filtration | $24K | 2025–2026 |
Descriptions, page references and contacts for Gladstone
Klarifi holds every Gladstone line item with its description, the page it appears on and the source document, plus 1 verified contact at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$718K
7 items
2026
$475K
2 items
2027
$310K
1 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 3 | $413K | 27% |
| Water Supply | 7 | $1M | 73% |
1 publicly owned treatment plant in Gladstone with 10 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Gladstone WWTP | 0.38 | MI0057676 | 10 |
Sources and methodology
Budgets and years are as published in Gladstone’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2022–2028 (10 line items).
Data refreshed September 11, 2026.