97 line items · $68M · starting 2026–2029 · 2 plans
Midland's published capital plans list 97 water, sewer and wastewater line items with a combined planning budget of $68M, of which 75 items worth $55M sit in the wastewater and sewer departments. The largest single item is Moorland Footing Drain Disconnection (Public) at $6M (2024–2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Moorland Footing Drain Disconnection (Public) | Sewer | Sewer rehabilitation and I&I | $6M | 2024–2026 |
| 2 | Water Plant Emergency Generator | Water Supply | Water treatment plants | $6M | 2029–2030 |
| 3 | Footing Drain Disconnections | Sewer | Sewer rehabilitation and I&I | $5M | 2024–2026 |
| 4 | Grit Removal Replace | Wastewater | Headworks, screening and grit | $5M | 2026–2028 |
| 5 | Sylvan Lane Upsizing | Sewer | Sewer rehabilitation and I&I | $5M | 2024–2026 |
| 6 | Footing Drain Disconnections | Wastewater | Sewer rehabilitation and I&I | $4M | 2024–2027 |
| 7 | Saginaw Road Sanitary Sewer Upsize/Stoneridge Force Main | Sewer | Force mains and interceptors | $4M | 2024–2025 |
| 8 | Cure-In-Place Pipe | Wastewater | Sewer rehabilitation and I&I | $3M | 2024–2025 |
| 9 | UV Disinfection | Wastewater | Disinfection and UV | $3M | 2028–2029 |
| 10 | UV Disinfection | Wastewater | Disinfection and UV | $3M | 2025–2027 |
87 more line items in Midland, with descriptions and contacts
Klarifi holds every Midland line item with its description, the page it appears on and the source document, plus 1 verified contact at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$47M
57 items
2026
$7M
14 items
2027
$2M
7 items
2028
$5M
11 items
2029
$7M
8 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 65 | $33M | 49% |
| Sewer | 10 | $22M | 32% |
| Water Supply | 22 | $13M | 19% |
1 publicly owned treatment plant in Midland with 7 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Bullock Creek High School Wwsl | 0.18 | MIG580077 | 7 |
Sources and methodology
Budgets and years are as published in Midland’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2030 (54 line items); CIP 2023–2028 (43 line items).
Data refreshed October 12, 2026.
Wastewater terms: Lift station · Inflow and infiltration · Sludge dewatering · WWTP · Centrate · Ozonation · all terms