Port Huron, Michigan: water and wastewater capital improvement projects

94 line items · $71M · starting 2026–2029 · 1 plan

Port Huron's published capital plans list 94 water, sewer and wastewater line items with a combined planning budget of $71M, of which 54 items worth $44M sit in the wastewater and sewer departments. The largest single item is Replace Odor Control System (Construction) at $8M (2025–2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Port Huron

The 10 largest water, sewer and wastewater line items in Port Huron’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Replace Odor Control System (Construction)WastewaterSCADA, controls and instrumentation$8M2025–2026
2Blue Water Bridge South AreaSewer$4M2028–2030
3Rehabilitation of Primary Tanks (8 Each)WastewaterStorage tanks and reservoirs$3M2024–2025
4Hospital Area Road and Utility Improvements - Phase 2Water DistributionWater mains and distribution$3M2028–2029
5Blue Water Bridge South AreaWater Distribution$3M2028–2030
6Rehabilitation of Splitter Box, Scum Tank, Scum Pump, Pipe Galley & StairsWastewaterPump stations$3M2024–2025
7Hospital Area Road and Utility Improvements - Phase 1Water DistributionWater mains and distribution$2M2024–2025
8Rehabilitation of Final ClarifiersWastewaterClarifiers and settling$2M2024–2025
9Huron Avenue - Quay to Glenwood (MDOT)Water DistributionWater mains and distribution$2M2026–2027
10Replace Secondary RoofWastewaterBuildings, HVAC and site work$2M2024–2025

84 more line items in Port Huron, with descriptions and contacts

Klarifi holds every Port Huron line item with its description, the page it appears on and the source document, plus 17 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

Before 2026

$37M

52 items

2026

$10M

17 items

2027

$7M

11 items

2028

$13M

7 items

2029

$3M

7 items

By department

Line items and planning budgets by department, Port Huron.
DepartmentLine itemsBudgetShare
Wastewater32$29M41%
Sewer22$15M21%
Water Supply20$7M10%
Water Distribution20$20M28%

Project types in Port Huron's plan

Wastewater treatment plants in Port Huron

1 publicly owned treatment plant in Port Huron with 4 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
City Of Port Huron Wastewater Treatment Plant6.03MI00238334

Other Michigan cities with capital plans

Port Huron capital plan questions

Sources and methodology

Budgets and years are as published in Port Huron’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2024–2030 (94 line items).

Data refreshed September 11, 2026.