6 line items · $2M · starting 2026–2028 · 1 plan
Saint Ignace's published capital plans list 6 water, sewer and wastewater line items with a combined planning budget of $2M, of which 2 items worth $175K sit in the wastewater and sewer departments. The largest single item is Replace Water Mains (591 RR&I) at $1M (2027). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Replace Water Mains (591 RR&I) | Water Distribution | Water mains and distribution | $1M | 2027 |
| 2 | Rehabilitate Water Treatment Plant Equipment (591 RR&I) | Water Supply | Water treatment plants | $180K | 2025–2026 |
| 3 | New Huron Street Lift Station | Wastewater | Lift stations | $100K | 2026 |
| 4 | Rehabilitate Water Treatment Plant Equipment (591 RR&I) | Water Supply | Water treatment plants | $87K | 2027 |
| 5 | Marley Street High-Capacity Pump (591 RR&I) | Wastewater | Pump stations | $75K | 2028 |
| 6 | American Legion Park Swing set | Water Supply | — | $20K | 2028 |
Descriptions, page references and contacts for Saint Ignace
Klarifi holds every Saint Ignace line item with its description, the page it appears on and the source document, plus 6 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$180K
1 items
2026
$100K
1 items
2027
$2M
2 items
2028
$95K
2 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 2 | $175K | 9% |
| Water Supply | 3 | $287K | 15% |
| Water Distribution | 1 | $1M | 76% |
1 publicly owned treatment plant in Saint Ignace with 6 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| St Ignace WWTP | 0.29 | MI0020699 | 6 |
Sources and methodology
Budgets and years are as published in Saint Ignace’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2024–2029 (6 line items).
Data refreshed September 11, 2026.