Oxford, Ohio: water and wastewater capital improvement projects

Water, sewer and wastewater line items in Oxford’s published capital improvement plans and adopted budgets, with budgets, years and the source documents.

Planned budget
$26M
Line items
57
Wastewater and sewer
$11M
16 line items
Starting
2026–2029
Plan
1

Oxford's published capital plans list 57 water, sewer and wastewater line items with a combined planning budget of $26M, of which 16 items worth $11M sit in the wastewater and sewer departments. The largest single item is Water Treatment Plant Improvements*(1) at $9M (2025). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Oxford

The 10 largest water, sewer and wastewater line items in Oxford’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Water Treatment Plant Improvements*(1)Water SupplyWastewater treatment plant upgrades$9M2025
2Biotower Media Replacement*(2)Wastewater—$6M2025
3Repair Concrete primary tanks and replace new drive, rake arms, walkways and hardware (3)WastewaterStorage tanks and reservoirs$3M2026
4New Raw Water Well #9Water SupplyWells and groundwater$1M2029
5Phosphorus RemovalWastewaterNutrient removal$500K2025
6Sanitary Sewer System ImprovementsSewerSewer rehabilitation and I&I$500K2025–2029
7Water System ImprovementsWater DistributionWater mains and distribution$500K2025–2029
8Contingency Water System Connection Between City and South West RegionalWater Distribution—$340K2026
9Lead Service Line ReplacementsWater DistributionLead service line replacement$300K2025–2029
10Upgrade Water Main on HilltopWater DistributionWater mains and distribution$300K2029
47 more line items in Oxford, with descriptions and contacts
Klarifi holds every Oxford line item with its description, the page it appears on and the source document, plus 3 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Create a free account

Planned spend by start year

Before 2026
$18M
27 items
2026
$4M
12 items
2027
$985K
6 items
2028
$1M
7 items
2029
$2M
5 items

By department

Line items and planning budgets by department, Oxford.
DepartmentLine itemsBudgetShare
Wastewater11$10M37%
Sewer5$1M4%
Water Supply12$11M41%
Water Distribution29$5M19%

Project types in Oxford's plan

  • Wastewater treatment plant upgrades
    1 line items
    $9M
  • $3M
  • $3M
  • $1M
  • $655K
  • Nutrient removal
    1 line items
    $500K
  • $300K
  • $268K

Wastewater treatment plants in Oxford

1 publicly owned treatment plant in Oxford with 5 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
Oxford WWTP2.82OH00269305

Other Ohio cities with capital plans

All Ohio plans

Oxford capital plan questions

  1. How much is Oxford, OH planning to spend on water and sewer infrastructure?

    Oxford’s published capital plans list 57 water, sewer and wastewater line items with a combined budget of $26M, of which $11M is in the wastewater and sewer departments.

  2. What is the largest capital project in Oxford’s plan?

    Water Treatment Plant Improvements*(1), budgeted at $9M and scheduled for 2025 under the Water Supply department.

  3. When do Oxford’s water and sewer projects start?

    12 projects ($4M) start in 2026 and 6 projects ($985K) start in 2027. Budgets are as published in the plan and can change at adoption.

  4. How do I find the contacts and full project list for Oxford?

    Klarifi holds every line item with its description, page reference and source document, plus 3 verified contacts at the city’s treatment plants. The public page shows the ten largest items; the full list is available with a free trial.

Try Klarifi for free

Create your own trial account and explore how Klarifi can help you.

Try for freeOr book a demo
Wastewater market intelligence: facilities, permits, compliance and capital projects for North America and Europe.
© 2026 Klarifi ApS, Diplomvej 381, 2800 Kgs. Lyngby, Denmark
Public data refreshed Nov 2, 2026