Klarifi Logo
Try for freeLog in
Klarifi Logo

Danville, Virginia: water and wastewater capital improvement projects

13 line items · $69M · starting 2026–2029 · 1 plan

Danville's published capital plans list 13 water, sewer and wastewater line items with a combined planning budget of $69M, of which 10 items worth $38M sit in the wastewater and sewer departments. The largest single item is Southside Plant Improvements at $18M (2026–2027). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Danville

The 10 largest water, sewer and wastewater line items in Danville’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Southside Plant ImprovementsWastewaterWastewater treatment plant upgrades$18M2026–2027
2Water Line ReconstructionWater DistributionWater mains and distribution$16M2026–2030
3Lead Service Line ReplacementWater DistributionLead service line replacement$8M2026
4Westover Pumping Station RelocationSewerPump stations$8M2027
5Edgewood Tank UpgradeWater DistributionStorage tanks and reservoirs$6M2027
6Sanitary Sewer - New Housing SubdivisionWastewaterSewer rehabilitation and I&I$4M2027–2030
7Luna Lake Road SewersWastewaterSewer rehabilitation and I&I$3M2029–2030
8New Sewer Lines/Inflow & Infiltration ReductionWastewaterMembranes and filtration$2M2026–2030
9Sewer Line ReconstructionWastewaterSewer rehabilitation and I&I$2M2026–2030
10Fall Creek Sanitary Sewer Reconstruction & RehabWastewaterSewer rehabilitation and I&I$1M2027

3 more line items in Danville, with descriptions and contacts

Klarifi holds every Danville line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

2026

$45M

5 items

2027

$20M

6 items

2028

$800K

1 items

2029

$3M

1 items

By department

Line items and planning budgets by department, Danville.
DepartmentLine itemsBudgetShare
Wastewater9$31M45%
Sewer1$8M11%
Water Distribution3$30M44%

Project types in Danville's plan

Wastewater treatment plants in Danville

1 publicly owned treatment plant in Danville with 5 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
City Of Danville Northside WWTP5.03VAL0605935

Other Virginia cities with capital plans

Danville capital plan questions

Sources and methodology

Budgets and years are as published in Danville’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2026–2030 (13 line items).

Data refreshed September 11, 2026.

Try Klarifi for free

Create your own trial account and explore how Klarifi can help you.

Try for free