36 line items · $79M · starting 2026–2029 · 1 plan
Dunedin's published capital plans list 36 water, sewer and wastewater line items with a combined planning budget of $79M, of which 25 items worth $64M sit in the wastewater and sewer departments. The largest single item is Wastewater Treatment Plant Electrical System Upgrade at $18M (2025). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Wastewater Treatment Plant Electrical System Upgrade | Wastewater | Wastewater treatment plant upgrades | $18M | 2025 |
| 2 | Pipe Lining Project | Wastewater | Sewer rehabilitation and I&I | $8M | 2025–2030 |
| 3 | Wastewater Treatment Plant Reclaim Storage Tank On Site | Wastewater | Wastewater treatment plant upgrades | $8M | 2028–2029 |
| 4 | Deep Well Injection Study | Wastewater | Wells and groundwater | $7M | 2028–2029 |
| 5 | Wastewater Lift Stations Rehabilitation | Wastewater | Lift stations | $6M | 2025–2030 |
| 6 | Water Production Well Facilities | Water Supply | Water treatment plants | $4M | 2024–2029 |
| 7 | Utility Relocation on Curlew | Water Distribution | Stormwater and flood resilience | $3M | 2026 |
| 8 | Wastewater Lift Station Force Main Replacements | Wastewater | Lift stations | $3M | 2025 |
| 9 | Greensand Filter Rehabilitation | Water Distribution | Membranes and filtration | $3M | 2027 |
| 10 | Virginia Street Water Main Replacement | Water Distribution | Water mains and distribution | $2M | 2025 |
26 more line items in Dunedin, with descriptions and contacts
Klarifi holds every Dunedin line item with its description, the page it appears on and the source document, plus 3 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$55M
27 items
2026
$5M
4 items
2027
$3M
1 items
2028
$14M
3 items
2029
$2M
1 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 24 | $64M | 81% |
| Sewer | 1 | $75K | 0% |
| Water Supply | 3 | $5M | 7% |
| Water Distribution | 8 | $10M | 12% |
1 publicly owned treatment plant in Dunedin with 2 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| City Of Dunedin Wastewater Treatment Plant | 3.46 | FL0021326 | 2 |
Sources and methodology
Budgets and years are as published in Dunedin’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2024–2030 (36 line items).
Data refreshed September 11, 2026.