Florida water and wastewater capital improvement plans

1,229 planned projects · $11.2B · 22 cities · 23 plans

The 23 capital improvement plans and adopted budgets Klarifi has extracted for Florida list 1,229 water, sewer and wastewater line items with a combined planning budget of $11.2B across 22 cities. Jacksonville has the largest plan at $3.6B. Each city page lists its largest projects with budgets and years, links the source document and the city's treatment plants.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

Wastewater plants in FloridaFlorida NPDES permits →

Cities in Florida with water and sewer capital plans

Florida cities ranked by the combined planning budget of their water, sewer and wastewater line items.
#CityLine itemsBudgetPlans
1Jacksonville217$3.6B1
2Myakka City131$1.8B1
3Cape Coral36$1.1B1
4Saint Petersburg181$942M1
5Orlando63$640M1
6Fort Myers29$556M1
7Fort Lauderdale109$543M2
8Winter Haven49$347M1
9Riviera Beach18$311M1
10Hollywood48$278M1
11Delray Beach19$171M1
12Pompano Beach25$160M1
13Sarasota40$153M1
14Cocoa89$127M1
15North Miami Beach12$95M1
16Milton21$83M1
17Dunedin36$79M1
18Plant City16$51M1
19Vero Beach46$51M1
20Bartow17$25M1
21Crystal River23$8M1
22Tampa4$2M1

Planned spend by start year

Before 2026

$8.0B

777 items

2026

$1.3B

181 items

2027

$741M

106 items

2028

$610M

89 items

2029

$293M

50 items

2030

$215M

26 items

By department

Line items and planning budgets by utility department, Florida.
DepartmentLine itemsBudgetShare
Wastewater378$2.5B22%
Sewer322$4.2B37%
Water Supply272$2.6B23%
Water Distribution257$2.0B18%

Project types in Florida

Wastewater treatment plant upgrades · 68 · $2.8BWater mains and distribution · 204 · $1.3BSewer rehabilitation and I&I · 85 · $1.1BWater treatment plants · 71 · $835MMembranes and filtration · 43 · $633MPump stations · 90 · $460MWells and groundwater · 41 · $459MBiosolids, sludge and dewatering · 29 · $410MLift stations · 81 · $339MForce mains and interceptors · 56 · $271M

The largest planned projects in Florida

The ten largest water, sewer and wastewater line items in Florida plans by planning budget.
#ProjectCityTypeBudgetYears
1SWDE - Buckman Water Reclamation Facility ImprovementsJacksonville, FLWastewater treatment plant upgrades$366M2024–2028
2North Regional Water Reclamation Facility Expansion 12.5 MGDMyakka City, FLWastewater treatment plant upgrades$255M2026–2030
3Buckman Reclamation Facility - Biosolids Conversion - Process FacilityJacksonville, FLBiosolids, sludge and dewatering$253M2024–2028
4New Water Treatment FacilityRiviera Beach, FLWastewater treatment plant upgrades$250M2025–2029
5North WRF 8 MGD (Phase 1) Expandable to 17 MGDCape Coral, FLWastewater treatment plant upgrades$243M2025–2027
6Blacks Ford Reclamation Facility - Expansion from 6 to 12 MGDJacksonville, FLWastewater treatment plant upgrades$211M2024–2028
7WWTP #3 ExpansionWinter Haven, FLWastewater treatment plant upgrades$180M2025–2029
8Buffalo Creek Reverse Osmosis Water Treatment PlantMyakka City, FLMembranes and filtration$174M2025–2031
9Southwest Water Reclamation Facility Expansion to 18 MGDMyakka City, FLWastewater treatment plant upgrades$165M2025–2028
10Galvanized Pipe Replacement - ProgramJacksonville, FLWater mains and distribution$165M2024–2028

All 1,229 Florida line items in Klarifi

Every project with its description, page reference and source document, filterable by city, department, type, budget and year, linked to the plants and decision-makers in each city.

Start a free trial

Florida capital plan questions

Sources and methodology

Budgets and years are as published in each city’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Data refreshed September 11, 2026.