13 line items · $12M · starting 2026–2027 · 1 plan
Lexington's published capital plans list 13 water, sewer and wastewater line items with a combined planning budget of $12M, of which 4 items worth $4M sit in the wastewater and sewer departments. The largest single item is Water Filtration Plant Rehab at $5M (2025–2027). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Water Filtration Plant Rehab | Water Supply | Membranes and filtration | $5M | 2025–2027 |
| 2 | Gravity Sewer Rehabilitation | Sewer | Sewer rehabilitation and I&I | $3M | 2024–2027 |
| 3 | Water Main Replacement 3‐6 | Water Distribution | Water mains and distribution | $1M | 2024–2027 |
| 4 | New Water Storage Tank | Water Supply | Storage tanks and reservoirs | $1M | 2025–2027 |
| 5 | Boynton Lift Station Force Main | Sewer | Lift stations | $1M | 2024–2027 |
| 6 | Lagoon Rehab | Sewer | Lagoons and ponds | $325K | 2024–2025 |
| 7 | West End Booster Station New | Water Supply | Pump stations | $250K | 2027–2028 |
| 8 | Huron Lift Station Rehab | Sewer | Lift stations | $250K | 2024–2027 |
| 9 | West End Booster Station Exist | Water Supply | Pump stations | $163K | 2026–2027 |
| 10 | Intake/Low Lift Upgrades | Water Supply | — | $156K | 2026–2027 |
3 more line items in Lexington, with descriptions and contacts
Klarifi holds every Lexington line item with its description, the page it appears on and the source document, plus 8 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$12M
8 items
2026
$319K
2 items
2027
$406K
3 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Sewer | 4 | $4M | 36% |
| Water Supply | 6 | $7M | 53% |
| Water Distribution | 3 | $1M | 11% |
1 publicly owned treatment plant in Lexington with 13 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Lexington Wwsl | — | MIG580356 | 13 |
Sources and methodology
Budgets and years are as published in Lexington’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2024–2030 (13 line items).
Data refreshed September 11, 2026.