Marshall, Michigan: water and wastewater capital improvement projects

61 line items · $73M · starting 2026–2030 · 2 plans

Marshall's published capital plans list 61 water, sewer and wastewater line items with a combined planning budget of $73M, of which 21 items worth $45M sit in the wastewater and sewer departments. The largest single item is Headworks & Equalization Basin Improvements at $20M (2025–2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Marshall

The 10 largest water, sewer and wastewater line items in Marshall’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Headworks & Equalization Basin ImprovementsWastewaterHeadworks, screening and grit$20M2025–2026
2Headworks & Equalization Basin ImprovementsWastewaterHeadworks, screening and grit$20M2025–2026
3Build New Iron Removal PlantWater Supply$5M2030–2031
4New Water Treatment PlantWater SupplyWater treatment plants$5M2028–2029
5Hanover Street Marshall to KalamazooWater DistributionLead service line replacement$2M2028–2029
6Sewer LiningWastewaterSewer rehabilitation and I&I$1M2025–2031
7Hanover St. water main replacement/water main liningWater DistributionWater mains and distribution$1M2028–2029
8Replace Water Main on N. GordonWater DistributionWater mains and distribution$963K2026–2027
9Replace 10" Cast Iron Water Main on High StWater DistributionWater mains and distribution$901K2027–2028
10Waldon Ponds ApartmentsWater DistributionWater mains and distribution$701K2027–2028

51 more line items in Marshall, with descriptions and contacts

Klarifi holds every Marshall line item with its description, the page it appears on and the source document, plus 22 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

Before 2026

$46M

26 items

2026

$4M

8 items

2027

$4M

11 items

2028

$10M

7 items

2029

$3M

4 items

2030

$7M

5 items

By department

Line items and planning budgets by department, Marshall.
DepartmentLine itemsBudgetShare
Wastewater20$45M61%
Sewer1$360K0%
Water Supply8$11M15%
Water Distribution32$18M24%

Project types in Marshall's plan

Wastewater treatment plants in Marshall

1 publicly owned treatment plant in Marshall. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
Marshall WWTP1.05MI00235400

Other Michigan cities with capital plans

Marshall capital plan questions

Sources and methodology

Budgets and years are as published in Marshall’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2025–2031 (33 line items); CIP 2024–2030 (28 line items).

Data refreshed September 11, 2026.