61 line items · $73M · starting 2026–2030 · 2 plans
Marshall's published capital plans list 61 water, sewer and wastewater line items with a combined planning budget of $73M, of which 21 items worth $45M sit in the wastewater and sewer departments. The largest single item is Headworks & Equalization Basin Improvements at $20M (2025–2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Headworks & Equalization Basin Improvements | Wastewater | Headworks, screening and grit | $20M | 2025–2026 |
| 2 | Headworks & Equalization Basin Improvements | Wastewater | Headworks, screening and grit | $20M | 2025–2026 |
| 3 | Build New Iron Removal Plant | Water Supply | — | $5M | 2030–2031 |
| 4 | New Water Treatment Plant | Water Supply | Water treatment plants | $5M | 2028–2029 |
| 5 | Hanover Street Marshall to Kalamazoo | Water Distribution | Lead service line replacement | $2M | 2028–2029 |
| 6 | Sewer Lining | Wastewater | Sewer rehabilitation and I&I | $1M | 2025–2031 |
| 7 | Hanover St. water main replacement/water main lining | Water Distribution | Water mains and distribution | $1M | 2028–2029 |
| 8 | Replace Water Main on N. Gordon | Water Distribution | Water mains and distribution | $963K | 2026–2027 |
| 9 | Replace 10" Cast Iron Water Main on High St | Water Distribution | Water mains and distribution | $901K | 2027–2028 |
| 10 | Waldon Ponds Apartments | Water Distribution | Water mains and distribution | $701K | 2027–2028 |
51 more line items in Marshall, with descriptions and contacts
Klarifi holds every Marshall line item with its description, the page it appears on and the source document, plus 22 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$46M
26 items
2026
$4M
8 items
2027
$4M
11 items
2028
$10M
7 items
2029
$3M
4 items
2030
$7M
5 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 20 | $45M | 61% |
| Sewer | 1 | $360K | 0% |
| Water Supply | 8 | $11M | 15% |
| Water Distribution | 32 | $18M | 24% |
1 publicly owned treatment plant in Marshall. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Marshall WWTP | 1.05 | MI0023540 | 0 |
Sources and methodology
Budgets and years are as published in Marshall’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2031 (33 line items); CIP 2024–2030 (28 line items).
Data refreshed September 11, 2026.