70 line items · $16M · starting 2026–2030 · 1 plan
Mount Pleasant's published capital plans list 70 water, sewer and wastewater line items with a combined planning budget of $16M, of which 18 items worth $3M sit in the wastewater and sewer departments. The largest single item is Lime Residual Removal at $2M (2025–2029). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Lime Residual Removal | Water Supply | Lagoons and ponds | $2M | 2025–2029 |
| 2 | Remove 10,000 Yds | Water Supply | Lagoons and ponds | $2M | 2025–2029 |
| 3 | Facility Improvements and Replacements | Water Supply | — | $1M | 2025–2030 |
| 4 | Distribution System Replacement | Water Supply | Water mains and distribution | $1M | 2025–2030 |
| 5 | Lift Station Improvements and Replacements | Water Supply | Lift stations | $682K | 2025–2030 |
| 6 | Raw Water Reservoir | Water Supply | Storage tanks and reservoirs | $650K | 2029 |
| 7 | Meter Replacement | Water Supply | Meters and AMI | $396K | 2025–2029 |
| 8 | Replacement of water meters per meter rotation plan. | Wastewater | Meters and AMI | $396K | 2025–2030 |
| 9 | Source Water Equipment Rehabilitation | Water Supply | Vehicles and equipment | $386K | 2026–2028 |
| 10 | Upgrade facility HVAC system | Wastewater | Buildings, HVAC and site work | $330K | 2027 |
60 more line items in Mount Pleasant, with descriptions and contacts
Klarifi holds every Mount Pleasant line item with its description, the page it appears on and the source document, plus 28 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$9M
23 items
2026
$2M
15 items
2027
$1M
7 items
2028
$1M
11 items
2029
$2M
10 items
2030
$558K
4 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 18 | $3M | 17% |
| Water Supply | 52 | $13M | 83% |
2 publicly owned treatment plants in Mount Pleasant with 22 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Mt Pleasant WWTP | 1.88 | MI0023655 | 18 |
| Isabella Reservation WWTP | 0.33 | MI0054861 | 4 |
Sources and methodology
Budgets and years are as published in Mount Pleasant’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2030 (70 line items).