Pinckney, Michigan: water and wastewater capital improvement projects

10 line items · $1M · 1 plan

Pinckney's published capital plans list 10 water, sewer and wastewater line items with a combined planning budget of $1M, of which 6 items worth $1M sit in the wastewater and sewer departments. The largest single item is Muriel to Ashton at $555K (2025–2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Pinckney

The 10 largest water, sewer and wastewater line items in Pinckney’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Muriel to AshtonSewer$555K2025–2026
2KnollwoodSewer$295K2024–2025
3Valve ReplacementSewerWater mains and distribution$170K2025–2026
4Water Tower - SealantWater SupplyStorage tanks and reservoirs$120K2025–2026
5Headworks/Fine Screen BuildingSewerHeadworks, screening and grit$81K2024–2026
6ForcemainSewerForce mains and interceptors$24K2024–2026
7MXU replacementsWater Supply$20K2024–2026
8HydrantsWater SupplyWater mains and distribution$6K2024–2026
9Sensus Handheld Meter ReaderSewerMeters and AMI$5K2025–2026
10Meter ReplacementsWater SupplyMeters and AMI$3K2024–2026

Descriptions, page references and contacts for Pinckney

Klarifi holds every Pinckney line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

Before 2026

$1M

10 items

By department

Line items and planning budgets by department, Pinckney.
DepartmentLine itemsBudgetShare
Sewer6$1M88%
Water Supply4$149K12%

Wastewater treatment plants in Pinckney

No publicly owned treatment plant is recorded under Pinckney in the facility directory; the city may be served by a regional plant listed under another municipality. Browse all plants in Michigan.

Other Michigan cities with capital plans

Pinckney capital plan questions

Sources and methodology

Budgets and years are as published in Pinckney’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2021–2026 (10 line items).