30 line items · $27M · starting 2026–2030 · 1 plan
Saint Johns's published capital plans list 30 water, sewer and wastewater line items with a combined planning budget of $27M, of which 19 items worth $22M sit in the wastewater and sewer departments. The largest single item is Solids Handling Improvements ‐ Additional Digestors at $6M (2030–2031). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Solids Handling Improvements ‐ Additional Digestors | Wastewater | Biosolids, sludge and dewatering | $6M | 2030–2031 |
| 2 | TRLS Force Main Replacement | Wastewater | Force mains and interceptors | $4M | 2027–2028 |
| 3 | Two Additional 5‐Unit RBC Trains (Development Driven) | Wastewater | — | $4M | 2030–2031 |
| 4 | Inflow and Infiltration Program | Wastewater | Membranes and filtration | $3M | 2024–2028 |
| 5 | Water Main Replacement ‐ M‐21 Corridor Throughout City Limits | Water Distribution | Water mains and distribution | $2M | 2026–2031 |
| 6 | Single New Secondary Clarifier | Wastewater | Clarifiers and settling | $1M | 2030–2031 |
| 7 | Collection System ‐ Pipe Lining/Maintenance | Wastewater | Sewer rehabilitation and I&I | $1M | 2024–2030 |
| 8 | TRLS Service Area I&I Reduction | Wastewater | Sewer rehabilitation and I&I | $1M | 2026–2029 |
| 9 | Biosolids Mixing / Loading ‐ Wastewater Plant | Wastewater | Biosolids, sludge and dewatering | $800K | 2030–2031 |
| 10 | Lead & Copper Rule ‐ Service Line Replacement | Water Distribution | Water mains and distribution | $500K | 2024–2031 |
20 more line items in Saint Johns, with descriptions and contacts
Klarifi holds every Saint Johns line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$8M
21 items
2026
$3M
3 items
2027
$4M
2 items
2030
$12M
4 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 18 | $22M | 82% |
| Sewer | 1 | $260K | 1% |
| Water Supply | 3 | $455K | 2% |
| Water Distribution | 8 | $4M | 16% |
No publicly owned treatment plant is recorded under Saint Johns in the facility directory; the city may be served by a regional plant listed under another municipality. Browse all plants in Michigan.
Sources and methodology
Budgets and years are as published in Saint Johns’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2024–2030 (30 line items).
Data refreshed September 11, 2026.