12 line items · $9M · starting 2026–2027 · 1 plan
Collierville's published capital plans list 12 water, sewer and wastewater line items with a combined planning budget of $9M, of which 9 items worth $5M sit in the wastewater and sewer departments. The largest single item is Sewer System Improvements at $2M (2027–2029). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Sewer System Improvements | Sewer | Sewer rehabilitation and I&I | $2M | 2027–2029 |
| 2 | Water Distribution System Improvements | Water Distribution | Water mains and distribution | $2M | 2027–2029 |
| 3 | North Rowlett Water Line | Water Distribution | Water mains and distribution | $2M | 2025 |
| 4 | CIPP/SSES Sewer Improvements | Sewer | Sewer rehabilitation and I&I | $1M | 2026–2029 |
| 5 | Burrows Rd. Water/Sewer Improvement Project | Sewer | Sewer rehabilitation and I&I | $900K | 2025–2026 |
| 6 | Mt. Pleasant Sewer Improvement | Sewer | Sewer rehabilitation and I&I | $350K | 2025 |
| 7 | Hurdle St. Sewer Improvement Project | Sewer | Sewer rehabilitation and I&I | $250K | 2026 |
| 8 | Equipment - Backhoe | Sewer | Vehicles and equipment | $162K | 2027 |
| 9 | Emergency Generator Replacement - Water Plant #2 | Water Supply | Water treatment plants | $150K | 2026 |
| 10 | Emergency Generator - Wolf River Pump Station | Sewer | Pump stations | $145K | 2025 |
2 more line items in Collierville, with descriptions and contacts
Klarifi holds every Collierville line item with its description, the page it appears on and the source document, plus 4 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$3M
5 items
2026
$2M
4 items
2027
$4M
3 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Sewer | 9 | $5M | 59% |
| Water Supply | 1 | $150K | 2% |
| Water Distribution | 2 | $4M | 39% |
2 publicly owned treatment plants in Collierville with 8 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Collierville Northwest STP | 3.38 | TN0078841 | 3 |
| Town Of Collierville | 1.16 | TN0057461 | 5 |
Sources and methodology
Budgets and years are as published in Collierville’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2029 (12 line items).
Data refreshed September 11, 2026.