52 line items · $261M · starting 2026–2030 · 1 plan
Beaumont's published capital plans list 52 water, sewer and wastewater line items with a combined planning budget of $261M, of which 20 items worth $92M sit in the wastewater and sewer departments. The largest single item is Annual Waterline Replacement at $54M (2025–2030). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Annual Waterline Replacement | Water Supply | Water mains and distribution | $54M | 2025–2030 |
| 2 | Annual Collection System Renewal | Wastewater | Sewer rehabilitation and I&I | $37M | 2025–2030 |
| 3 | Lawson's Canal Maintenance Project | Water Distribution | Pump stations | $15M | 2025–2026 |
| 4 | Southeast Industrial Improvements (New | Water Supply | — | $10M | 2025–2026 |
| 5 | Southeast Industrial Improvements (New) | Wastewater | Sewer rehabilitation and I&I | $10M | 2025–2026 |
| 6 | Annual Water Production System Repairs | Water Supply | Water treatment plants | $9M | 2025–2030 |
| 7 | Pine Street Water Line Replacement 1 | Water Distribution | Water mains and distribution | $8M | 2030 |
| 8 | Pine Street Treated Water Resiliency Line | Water Distribution | Stormwater and flood resilience | $8M | 2025–2026 |
| 9 | Raw Water Delivery Line | Water Supply | Pump stations | $8M | 2025 |
| 10 | Pine Street Water Line Replacement 4 | Water Distribution | Water mains and distribution | $6M | 2030 |
42 more line items in Beaumont, with descriptions and contacts
Klarifi holds every Beaumont line item with its description, the page it appears on and the source document, plus 1 verified contact at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$202M
32 items
2026
$1M
2 items
2027
$4M
2 items
2028
$6M
3 items
2029
$2M
1 items
2030
$46M
12 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 19 | $87M | 33% |
| Sewer | 1 | $5M | 2% |
| Water Supply | 21 | $109M | 41% |
| Water Distribution | 11 | $61M | 23% |
1 publicly owned treatment plant in Beaumont with 24 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Hillebrandt WWTP | 47.3 | TX0046990 | 24 |
Sources and methodology
Budgets and years are as published in Beaumont’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2029 (52 line items).
Data refreshed September 11, 2026.