Laredo, Texas: water and wastewater capital improvement projects

74 line items · $846M · starting 2026–2029 · 1 plan

Laredo's published capital plans list 74 water, sewer and wastewater line items with a combined planning budget of $846M, of which 46 items worth $652M sit in the wastewater and sewer departments. The largest single item is South Laredo WWTP exp to 24 mgd at $138M (2027–2028). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Laredo

The 10 largest water, sewer and wastewater line items in Laredo’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1South Laredo WWTP exp to 24 mgdWastewaterWastewater treatment plant upgrades$138M2027–2028
2NLWWTP 3 MGD Expansion-District 6SewerWastewater treatment plant upgrades$75M2027–2029
3Expansion of North Laredo WWTPWastewaterWastewater treatment plant upgrades$44M2027–2029
4Zacate Creek WWTP ReconstructionWastewaterWastewater treatment plant upgrades$44M2027–2029
5Manadas Expansion to 9.5 MGDSewerWastewater treatment plant upgrades$44M2027–2028
6El Pico 12 MG ExpansionWastewater$33M2027
7Line Rehab & Contingency Water Break - AllWastewaterWater mains and distribution$32M2025–2029
8Connect Hendricks to mid sized JWTP extension lineWastewater$31M2027–2029
93 MG Cuatro Vientos Booster Station-District 1Water DistributionPump stations$28M2025–2026
1054 SS InterceptorSewerForce mains and interceptors$27M2025–2026

64 more line items in Laredo, with descriptions and contacts

Klarifi holds every Laredo line item with its description, the page it appears on and the source document, plus 69 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

Before 2026

$242M

31 items

2026

$14M

3 items

2027

$569M

36 items

2028

$250K

1 items

2029

$21M

3 items

By department

Line items and planning budgets by department, Laredo.
DepartmentLine itemsBudgetShare
Wastewater24$407M48%
Sewer22$245M29%
Water Distribution28$194M23%

Project types in Laredo's plan

Wastewater treatment plants in Laredo

7 publicly owned treatment plants in Laredo with 96 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
South Laredo WWTP16.98TX00853162
Laredo City Of Sewer Plant16.21TX002546181
North Laredo WWTP2.51TX00578015
Regional WWTF0.62TX01184430
Unitec Center WWTP0.28TX01269265
Penitas WWTP0.05TX01317762
Laredo/columbia Solidarity Bridge WWTF0.003TX01073951

Other Texas cities with capital plans

Laredo capital plan questions

Sources and methodology

Budgets and years are as published in Laredo’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2025–2029 (74 line items).

Data refreshed September 11, 2026.