12 line items · $7M · starting 2026–2029 · 1 plan
Duvall's published capital plans list 12 water, sewer and wastewater line items with a combined planning budget of $7M, of which 4 items worth $629K sit in the wastewater and sewer departments. The largest single item is Crestview Estates Reservoir Improvements and Recoating at $3M (2027–2029). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Crestview Estates Reservoir Improvements and Recoating | Water Supply | Storage tanks and reservoirs | $3M | 2027–2029 |
| 2 | Big Rock Road Reservoir Re-coating and Inlet/ Outlet Improvements | Water Supply | Storage tanks and reservoirs | $2M | 2025–2026 |
| 3 | 8" Water Main in 1st Ave from NE Stephens to NE Valley Street | Water Distribution | Water mains and distribution | $329K | 2026 |
| 4 | Electrical Upgrades | Wastewater | Generators, power and electrical | $306K | 2027 |
| 5 | Tolt 1 Supply Station Improvements | Water Supply | — | $291K | 2027 |
| 6 | Tolt 2 Supply Station Improvements | Water Supply | — | $279K | 2027 |
| 7 | Sewer Plan Update | Sewer | Sewer rehabilitation and I&I | $250K | 2027 |
| 8 | 615 Zone Pump Station Improvements | Water Supply | Pump stations | $238K | 2025–2026 |
| 9 | 485 Zone to 555 Zone and reconfigure existing PRV's and Pressure Relief Station | Water Distribution | — | $220K | 2025 |
| 10 | 8" Water Main in Bruett Rd from 3rd Ave NE to 3rd PI NE | Water Distribution | Water mains and distribution | $193K | 2026 |
2 more line items in Duvall, with descriptions and contacts
Klarifi holds every Duvall line item with its description, the page it appears on and the source document. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$2M
3 items
2026
$541K
3 items
2027
$4M
5 items
2029
$54K
1 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 3 | $379K | 6% |
| Sewer | 1 | $250K | 4% |
| Water Supply | 5 | $5M | 79% |
| Water Distribution | 3 | $742K | 11% |
No publicly owned treatment plant is recorded under Duvall in the facility directory; the city may be served by a regional plant listed under another municipality. Browse all plants in Washington.
Sources and methodology
Budgets and years are as published in Duvall’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2030 (12 line items).
Data refreshed September 11, 2026.