244 line items · $518M · starting 2026–2030 · 1 plan
Spokane's published capital plans list 244 water, sewer and wastewater line items with a combined planning budget of $518M, of which 139 items worth $260M sit in the wastewater and sewer departments. The largest single item is Metering at $20M (2025–2030). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Metering | Water Supply | Meters and AMI | $20M | 2025–2030 |
| 2 | Well Electric Well Station Update | Water Supply | Wells and groundwater | $19M | 2025–2030 |
| 3 | Clarke Ave Lift Station Rehab | Wastewater | Lift stations | $15M | 2027–2029 |
| 4 | Northeast Stormwater Improvements | Wastewater | Stormwater and flood resilience | $11M | 2025–2028 |
| 5 | Secondary Clarifier Mechanism and Cover | Wastewater | Clarifiers and settling | $10M | 2027–2030 |
| 6 | Washington Basin Stormwater Separation | Wastewater | Stormwater and flood resilience | $9M | 2025–2029 |
| 7 | Shawnee Booster Station Rehabilitation | Water Supply | Pump stations | $8M | 2025–2028 |
| 8 | Coeur D'Alene to Milton Booster Station Transmission Main | Water Distribution | Pump stations | $8M | 2027–2029 |
| 9 | Freya Distribution Main (21st to 13th) | Water Distribution | Water mains and distribution | $8M | 2025–2026 |
| 10 | Northwest Terrace Lift Station Replacement | Wastewater | Lift stations | $8M | 2028–2029 |
234 more line items in Spokane, with descriptions and contacts
Klarifi holds every Spokane line item with its description, the page it appears on and the source document, plus 4 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$284M
126 items
2026
$60M
24 items
2027
$68M
29 items
2028
$61M
25 items
2029
$36M
19 items
2030
$8M
21 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 139 | $260M | 50% |
| Water Supply | 62 | $179M | 35% |
| Water Distribution | 43 | $79M | 15% |
1 publicly owned treatment plant in Spokane with 4 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Riverside Park Water Reclamation Facility | 31.72 | WA0024473 | 4 |
Sources and methodology
Budgets and years are as published in Spokane’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2025–2030 (244 line items).
Data refreshed September 11, 2026.