Cape Girardeau, Missouri: water and wastewater capital improvement projects

27 line items · $132M · starting 2026–2029 · 1 plan

Cape Girardeau's published capital plans list 27 water, sewer and wastewater line items with a combined planning budget of $132M, of which 4 items worth $13M sit in the wastewater and sewer departments. The largest single item is Medium Priority Watermain Improvements at $42M (2034–2035). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Cape Girardeau

The 10 largest water, sewer and wastewater line items in Cape Girardeau’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Medium Priority Watermain ImprovementsWater DistributionWater mains and distribution$42M2034–2035
2High Priority Watermain ImprovementsWater DistributionWater mains and distribution$28M2029–2034
3I&I Program - Cured-In-Place-Pipe RepairsSewerSewer rehabilitation and I&I$9M2026–2029
4Addition of Primary SCU-4 & Secondary SSB-4Water DistributionWastewater treatment plant upgrades$9M2025–2026
5Lime System ImprovementsWater DistributionWastewater treatment plant upgrades$6M2024–2025
6Annual CIST Street RepairWater DistributionWater mains and distribution$5M2024–2034
7Bertling Street 30" Water MainWater DistributionWater mains and distribution$4M2028–2034
8Water Tank Asset Management ProgramWater DistributionStorage tanks and reservoirs$4M2024–2034
9WWTP IPS Automatic Screen - Phase 2WastewaterHeadworks, screening and grit$4M2024–2025
10College Booster Pump StationWater DistributionPump stations$3M2026–2027

17 more line items in Cape Girardeau, with descriptions and contacts

Klarifi holds every Cape Girardeau line item with its description, the page it appears on and the source document, plus 2 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

Before 2026

$34M

12 items

2026

$15M

6 items

2028

$11M

6 items

2029

$28M

1 items

2032 and later

$43M

2 items

By department

Line items and planning budgets by department, Cape Girardeau.
DepartmentLine itemsBudgetShare
Wastewater1$4M3%
Sewer3$10M7%
Water Supply1$2M1%
Water Distribution22$116M89%

Project types in Cape Girardeau's plan

Wastewater treatment plants in Cape Girardeau

1 publicly owned treatment plant in Cape Girardeau. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
Cape Girardeau WWTP4.36MO01363280

Other Missouri cities with capital plans

Cape Girardeau capital plan questions

Sources and methodology

Budgets and years are as published in Cape Girardeau’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2024–2029 (27 line items).

Data refreshed September 11, 2026.