333 planned projects · $585M · 12 cities · 13 plans
The 13 capital improvement plans and adopted budgets Klarifi has extracted for New York list 333 water, sewer and wastewater line items with a combined planning budget of $585M across 12 cities. Syracuse has the largest plan at $309M. Each city page lists its largest projects with budgets and years, links the source document and the city's treatment plants.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | City | Line items | Budget | Plans |
|---|---|---|---|---|
| 1 | Syracuse | 75 | $309M | 2 |
| 2 | Plattsburgh | 29 | $79M | 1 |
| 3 | Watertown | 112 | $76M | 1 |
| 4 | Long Beach | 13 | $30M | 1 |
| 5 | Bethlehem | 42 | $26M | 1 |
| 6 | Yonkers | 3 | $23M | 1 |
| 7 | Peekskill | 4 | $18M | 1 |
| 8 | Rome | 27 | $11M | 1 |
| 9 | Schenectady | 9 | $6M | 1 |
| 10 | Oneonta | 12 | $3M | 1 |
| 11 | Corning | 6 | $3M | 1 |
Before 2026
$129M
156 items
2026
$352M
106 items
2027
$44M
41 items
2028
$27M
13 items
2029
$29M
15 items
2030
$4M
2 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 26 | $23M | 4% |
| Sewer | 103 | $122M | 21% |
| Water Supply | 144 | $147M | 25% |
| Water Distribution | 60 | $293M | 50% |
| # | Project | City | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | Lead Service Line Replacements | Syracuse, NY | Lead service line replacement | $150M | 2026–2031 |
| 2 | Water Main Replacement | Syracuse, NY | Water mains and distribution | $48M | 2026–2031 |
| 3 | Sewer Reconstruction | Syracuse, NY | Sewer rehabilitation and I&I | $29M | 2026–2031 |
| 4 | Water Systems Improvements | Yonkers, NY | — | $22M | 2026–2029 |
| 5 | Mead Dam Improvement Construction | Plattsburgh, NY | — | $20M | 2029 |
| 6 | Chlorine Gas Conversion to Onsite Generation | Syracuse, NY | Disinfection and UV | $19M | 2028–2029 |
| 7 | Eastwood Sewer Reconstruction/Lining | Syracuse, NY | Sewer rehabilitation and I&I | $14M | 2026 |
| 8 | Value of Capital Projects Supervised | Syracuse, NY | — | $12M | 2024–2026 |
| 9 | Elevated Tank Repl/Standpipe Demolition | Long Beach, NY | Storage tanks and reservoirs | $10M | 2027 |
| 10 | Raw Transmission Line Replacements | Plattsburgh, NY | Water mains and distribution | $9M | 2025–2029 |
All 333 New York line items in Klarifi
Every project with its description, page reference and source document, filterable by city, department, type, budget and year, linked to the plants and decision-makers in each city.
Sources and methodology
Budgets and years are as published in each city’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Data refreshed September 11, 2026.