27 line items · $92M · starting 2026–2029 · 1 plan
Ashland's published capital plans list 27 water, sewer and wastewater line items with a combined planning budget of $92M, of which 11 items worth $13M sit in the wastewater and sewer departments. The largest single item is 7.0 MGD Water Treatment Plant at $52M (2024–2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.
A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.
| # | Project | Department | Type | Budget | Years |
|---|---|---|---|---|---|
| 1 | 7.0 MGD Water Treatment Plant | Water Supply | Water treatment plants | $52M | 2024–2026 |
| 2 | 7.0 MGD Water Treatment Plant Construction Adminstration | Water Supply | Water treatment plants | $7M | 2024–2026 |
| 3 | Dam Safety Improvements | Water Supply | Stormwater and flood resilience | $7M | 2024–2025 |
| 4 | Distribution Pipe Projects | Water Distribution | Water mains and distribution | $5M | 2024–2029 |
| 5 | WWTP Process Improvements (Headworks) | Wastewater | Headworks, screening and grit | $4M | 2024–2025 |
| 6 | Upsize Bear Creek Intercceptor from Wightman Street to Tolman Creek Road | Sewer | Force mains and interceptors | $2M | 2024–2028 |
| 7 | N Phoenix Road Pipe Improvements | Water Distribution | Water mains and distribution | $2M | 2028–2029 |
| 8 | Annual Pipe Replacement | Water Distribution | Water mains and distribution | $2M | 2024–2029 |
| 9 | 24-inch Pipe Seismic Upgrades (Highway 99 Phoenix) | Water Distribution | Water mains and distribution | $2M | 2025 |
| 10 | Hillview BPS Replacement | Water Distribution | — | $2M | 2026–2027 |
17 more line items in Ashland, with descriptions and contacts
Klarifi holds every Ashland line item with its description, the page it appears on and the source document, plus 1 verified contact at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.
Before 2026
$86M
19 items
2026
$2M
2 items
2027
$75K
1 items
2028
$4M
4 items
2029
$671K
1 items
| Department | Line items | Budget | Share |
|---|---|---|---|
| Wastewater | 6 | $8M | 8% |
| Sewer | 5 | $5M | 5% |
| Water Supply | 4 | $66M | 72% |
| Water Distribution | 12 | $13M | 14% |
1 publicly owned treatment plant in Ashland with 15 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.
| Plant | Avg flow (MGD) | NPDES | Violations (3y) |
|---|---|---|---|
| Ashland WWTP | 1.71 | OR0026255 | 15 |
Sources and methodology
Budgets and years are as published in Ashland’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.
Documents: CIP 2024–2029 (27 line items).
Data refreshed September 11, 2026.