Pasadena, Texas: water and wastewater capital improvement projects

43 line items · $164M · starting 2026–2029 · 1 plan

Pasadena's published capital plans list 43 water, sewer and wastewater line items with a combined planning budget of $164M, of which 30 items worth $95M sit in the wastewater and sewer departments. The largest single item is Golden Acres WWTP SW Det & Flow Diver at $14M (2025–2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Pasadena

The 10 largest water, sewer and wastewater line items in Pasadena’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Golden Acres WWTP SW Det & Flow DiverWastewaterWastewater treatment plant upgrades$14M2025–2026
2Bay Area Blvd Water Pressure ImprovWater DistributionPump stations$11M2027
3Pas Ind Dis 36in Transmission Line Ph IIWater DistributionWater mains and distribution$11M2028
4Pas Ind Dis 36in Transmission Line Ph IWater DistributionWater mains and distribution$11M2027
5CWA Pump Station RehabilitationWater DistributionPump stations$9M2029
6Pasadena Industrial District 20 in LoopWater DistributionWater mains and distribution$9M2025
7Citywide Sanitary Sewer RehabSewerSewer rehabilitation and I&I$9M2025
8Citywide Waterline ReplacementWater DistributionWater mains and distribution$9M2025–2029
9North Main Lift StationWastewaterLift stations$8M2025–2027
10Vince Bayou WWTP Wet Weather FacilityWastewaterWastewater treatment plant upgrades$5M2025–2027

33 more line items in Pasadena, with descriptions and contacts

Klarifi holds every Pasadena line item with its description, the page it appears on and the source document, plus 4 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

Before 2026

$94M

30 items

2026

$13M

4 items

2027

$26M

4 items

2028

$18M

3 items

2029

$12M

2 items

By department

Line items and planning budgets by department, Pasadena.
DepartmentLine itemsBudgetShare
Wastewater25$81M49%
Sewer5$15M9%
Water Supply4$4M3%
Water Distribution9$64M39%

Project types in Pasadena's plan

Wastewater treatment plants in Pasadena

1 publicly owned treatment plant in Pasadena with 139 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
New Vince Bayou WWTF25TX0117528139

Other Texas cities with capital plans

Pasadena capital plan questions

Sources and methodology

Budgets and years are as published in Pasadena’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: CIP 2025–2029 (43 line items).

Data refreshed September 11, 2026.