Madison, Wisconsin: water and wastewater capital improvement projects

26 line items · $160M · starting 2027–2030 · 1 plan

Madison's published capital plans list 26 water, sewer and wastewater line items with a combined planning budget of $160M, of which 8 items worth $24M sit in the wastewater and sewer departments. The largest single item is Water Mains Replacement at $80M (2023–2025). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Madison

The 10 largest water, sewer and wastewater line items in Madison’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Water Mains ReplacementWater DistributionWater mains and distribution$80M2023–2025
2Water Utility Facility ImprovementsWater DistributionSCADA, controls and instrumentation$15M2023–2025
3Trenchless Sewer RehabilitationSewerSewer rehabilitation and I&I$12M2025–2030
4Water Utility Vehicles & EquipmentWater DistributionVehicles and equipment$7M2023–2025
5Well 27 Iron & Manganese MitigationWater DistributionWells and groundwater$7M2027–2028
6Unit Well 12 Conversion to a Two Zone WellWater DistributionWells and groundwater$5M2025–2026
7Sewer ReconstructionSewerSewer rehabilitation and I&I$4M2025–2030
8Lift Station & Force Main Rehabilitation and ReplacementSewerLift stations$4M2025–2030
9Water Meter and Fixed Network ProgramWater DistributionMeters and AMI$4M2023–2025
10High Point/Raymond/MidTownWater DistributionStormwater and flood resilience$3M2025–2030

16 more line items in Madison, with descriptions and contacts

Klarifi holds every Madison line item with its description, the page it appears on and the source document, plus 4 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

Before 2026

$148M

21 items

2027

$8M

2 items

2029

$4M

2 items

2030

$1M

1 items

By department

Line items and planning budgets by department, Madison.
DepartmentLine itemsBudgetShare
Sewer8$24M15%
Water Distribution18$137M85%

Wastewater treatment plants in Madison

1 publicly owned treatment plant in Madison with 2 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
EPA Superfund Site: Madison Metropolitan Sewerage District Lagoons39.37WIG0097562

Other Wisconsin cities with capital plans

Madison capital plan questions

Sources and methodology

Budgets and years are as published in Madison’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: Adopted Budget 2025 (26 line items).

Data refreshed October 5, 2026.

Wastewater terms: Lift station · Inflow and infiltration · Sludge dewatering · WWTP · Equalization tank · Centrate · all terms