Haverhill, Massachusetts: water and wastewater capital improvement projects

20 line items · $3M · starting 2026 · 1 plan

Haverhill's published capital plans list 20 water, sewer and wastewater line items with a combined planning budget of $3M, of which 8 items worth $730K sit in the wastewater and sewer departments. The largest single item is Capital Outlay at $665K (2025–2026). The ten largest items are listed below; the full list with descriptions and page references is in Klarifi.

A capital improvement plan (CIP) is a city’s multi-year budget for building and replacing infrastructure. The water, sewer and wastewater sections list each project with its budget and the years it is funded, which makes them the earliest public signal that a plant, pump station or pipe network is about to be upgraded, usually two to four years before a contract is awarded.

The largest water and sewer projects in Haverhill

The 10 largest water, sewer and wastewater line items in Haverhill’s capital plans by planning budget.
#ProjectDepartmentTypeBudgetYears
1Capital OutlayWater Supply$665K2025–2026
2Future Carbon Replacement FiltersWater SupplyMembranes and filtration$320K2025
3Catenary Screen RehabilitationWastewaterHeadworks, screening and grit$300K2026
4Infrastructure ExpenseWater Supply$250K2025–2026
5Infrastructure ExpenseWater Supply$220K2025–2026
6Vehicle ReplacementWater SupplyVehicles and equipment$165K2025–2026
7Miscellaneous EquipmentWastewaterVehicles and equipment$150K2026
8Computer Hardware/SoftwareWater SupplyVehicles and equipment$115K2025–2026
9Centrifuge ConveyorsWastewaterBiosolids, sludge and dewatering$100K2026
10Water Treatment MaintenanceWater DistributionWater treatment plants$100K2025–2026

10 more line items in Haverhill, with descriptions and contacts

Klarifi holds every Haverhill line item with its description, the page it appears on and the source document, plus 2 verified contacts at the city’s treatment plants. Track new plans as they are adopted and compare with similar projects in other cities.

Start a free trial

Planned spend by start year

Before 2026

$2M

12 items

2026

$730K

8 items

By department

Line items and planning budgets by department, Haverhill.
DepartmentLine itemsBudgetShare
Wastewater8$730K26%
Water Supply10$2M70%
Water Distribution2$130K5%

Project types in Haverhill's plan

Wastewater treatment plants in Haverhill

1 publicly owned treatment plant in Haverhill with 4 permit violations in the last three years. Each profile shows flow, permit, technology and compliance data.

PlantAvg flow (MGD)NPDESViolations (3y)
Haverhill Wastewater Treatment Facility6.58MAL1016214

Other Massachusetts cities with capital plans

Haverhill capital plan questions

Sources and methodology

Budgets and years are as published in Haverhill’s capital improvement plan or adopted budget. Klarifi extracts the water, sewer and wastewater line items from the published document, keeps the page reference for each one, and assigns a project type from the title and description with a keyword classifier. Figures are planning budgets, not awarded contracts, and can change when a plan is re-adopted.

Documents: Adopted Budget 2025–2026 (20 line items).

Data refreshed September 11, 2026.